Permit: TC-SOL-0525-00694
Permit Details
Apply Date:
05/27/2025
Applicant:
David Hosking
Description:
Rooftop Solar
Permit Reviews
Permit Number - TC-SOL-0525-00694
Permit Status: Complete
Permit Description: Rooftop Solar
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/27/2025 | RESIDENTIAL SOLAR APP v.1 | 05/27/2025 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-SOL-0525-00694
Permite Description: Rooftop Solar
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/07/2025 | BULD - Electrical Clearance | N/A | Partial Pass | 8.7.2025 Verbal clearance to TEP INCR 12:45PM for 125A main panel upgrade. Partial pass pending solar final. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-SOL-0525-00694
Permit Description: Rooftop Solar
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/12/2025 | BULD - Electrical Clearance | Passed | Approved solar - DGC Clearance to TEP is required for the solar meter | |