Permit: TC-SOL-0525-00608
Permit Details
Apply Date:
05/07/2025
Applicant:
Hailey McGraw
Description:
REV A: ELD UPDATED REV B: 09/08/2025 install 8.61kw residential roof mounted solar / 1 SolarEdge Energy Bank / New 125A load center
Permit Reviews
Permit Number - TC-SOL-0525-00608
Permit Status: Complete
Permit Description: REV A: ELD UPDATED
REV B: 09/08/2025
install 8.61kw residential roof mounted solar / 1 SolarEdge Energy Bank / New 125A load center
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/28/2025 | RESIDENTIAL SOLAR REVISION v.1 | 05/28/2025 | APPROVED |
| 09/08/2025 | RESIDENTIAL SOLAR REVISION v.1 | 09/08/2025 | APPROVED |
| 05/07/2025 | RESIDENTIAL SOLAR APP v.1 | 05/07/2025 | APPROVED |
Completed Inspections
Permit Status: Complete
Permit Number: TC-SOL-0525-00608
Permit Description: REV A: ELD UPDATED
REV B: 09/08/2025
install 8.61kw residential roof mounted solar / 1 SolarEdge Energy Bank / New 125A load center
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/12/2025 | BULD - Electrical Clearance | Passed | Approved solar and battery installation - DGC/BAT Clearance to TEP is required for the solar meter | |
| 09/12/2025 | COT - RSOL - Electrical Final Solar Project | Passed |