Permit Details

Status:
Complete
Type:
Solar
Apply Date:
04/04/2025
Applicant:
Hailey McGraw
Description:
Rev.4 REV A: THE FOLLOWING HAS BEEN REVISED: UTILITY ISOLATION DISCONNECT MOVED 10' WITHIN MAIN SERIVCE PANEL REV B: THE FOLLOWING HAS BEEN REVISED: UTILITY ISOLATION MOVED ON PV-2 NEXT TO THE MSP/METER 10.25 kW DC System- Roof Mount PV - W/ Storage - Derate

Permit Reviews

Permit Number - TC-SOL-0425-00430
Permit Status: Complete
Permit Description: Rev.4 REV A: THE FOLLOWING HAS BEEN REVISED: UTILITY ISOLATION DISCONNECT MOVED 10' WITHIN MAIN SERIVCE PANEL REV B: THE FOLLOWING HAS BEEN REVISED: UTILITY ISOLATION MOVED ON PV-2 NEXT TO THE MSP/METER 10.25 kW DC System- Roof Mount PV - W/ Storage - Derate
Start Date Submittal Complete Date Status  
05/13/2025 RESIDENTIAL SOLAR REVISION v.1 05/13/2025 APPROVED Review Details
04/04/2025 RESIDENTIAL SOLAR APP v.1 04/04/2025 APPROVED Review Details
07/22/2025 RESIDENTIAL SOLAR REVISION v.1 07/22/2025 APPROVED Review Details
05/29/2025 RESIDENTIAL SOLAR REVISION v.1 05/29/2025 APPROVED Review Details
04/28/2025 RESIDENTIAL SOLAR REVISION v.1 04/28/2025 APPROVED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: TC-SOL-0425-00430
Permit Description: Rev.4 REV A: THE FOLLOWING HAS BEEN REVISED: UTILITY ISOLATION DISCONNECT MOVED 10' WITHIN MAIN SERIVCE PANEL REV B: THE FOLLOWING HAS BEEN REVISED: UTILITY ISOLATION MOVED ON PV-2 NEXT TO THE MSP/METER 10.25 kW DC System- Roof Mount PV - W/ Storage - Derate
Total Completed Inspections - 2
Date Description Inspector Results Comments
09/25/2025 BULD - Electrical Clearance Passed 9.25.2025
Clearance to TEP DGC/BAT. Corrections made to prior inspection.
09/25/2025 COT - RSOL - Electrical Final Solar Project Passed 9.25.2025
Corrections made to prior inspection.