Permit: TC-RES-1225-05958
Permit Details
Status:
Inspections
Type:
Residential Building - One or Two Family
Address:
1226 S AVENIDA SIRIO
Address NEW:
1226 S AVENIDA SIRIO
Apply Date:
12/12/2025
Applicant:
Tommy Do
Description:
REV_1, Proposed Meter Revision; Roof mounted solar install; adding to existing PV system new system: DC 5.67 kW / AC 4.48 kW ; 14 modules derate of a main breaker from 200A to 175A
Permit Reviews
Permit Number - TC-RES-1225-05958
Permit Status: Inspections
Permit Description: REV_1, Proposed Meter Revision; Roof mounted solar install; adding to existing PV system
new system: DC 5.67 kW / AC 4.48 kW ; 14 modules
derate of a main breaker from 200A to 175A
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/15/2025 | RESIDENTIAL SOLAR v.1 | 12/22/2025 | APPROVED |
| 12/26/2025 | RESIDENTIAL SOLAR REVISION v.1 | 01/02/2026 | APPROVED |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-RES-1225-05958
Permite Description: REV_1, Proposed Meter Revision; Roof mounted solar install; adding to existing PV system
new system: DC 5.67 kW / AC 4.48 kW ; 14 modules
derate of a main breaker from 200A to 175A
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/20/2026 | BULD - Electrical Clearance | N/A | Partial Pass | Partial pass pending solar CLEARANCE INCR |
| 01/21/2026 | COT - RSOL - Electrical Final Solar Project | N/A | Canceled |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-RES-1225-05958
Permit Description: REV_1, Proposed Meter Revision; Roof mounted solar install; adding to existing PV system
new system: DC 5.67 kW / AC 4.48 kW ; 14 modules
derate of a main breaker from 200A to 175A
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/22/2026 | BULD - Electrical Clearance | Passed | Passed solar final 1/22/26 CLEARANCE DGC | |
| 01/22/2026 | COT - RSOL - Electrical Final Solar Project | Passed | Passed solar final 1/22/26 CLEARANCE DGC | |
| 01/22/2026 | RSBU - Building Final | Passed | Passed solar final 1/22/26 CLEARANCE DGC |