Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Address:
2216 E 5TH ST
Address NEW:
2216 E 5TH ST
Apply Date:
12/03/2024
Applicant:
TFS Solar
Description:
Roof mount 8.60kW DC photovoltaic solar system; 20 modules with microinverters, 2 branches, PV combiner Box, Supply Side Tap between 320A Meter, PV system with 40A fuse OCP, and existing 200A fused service disconnect. Existing 200A MLO load center with 200A bus.

Permit Reviews

Permit Number - TC-RES-1224-07010
Permit Status: Complete
Permit Description: Roof mount 8.60kW DC photovoltaic solar system; 20 modules with microinverters, 2 branches, PV combiner Box, Supply Side Tap between 320A Meter, PV system with 40A fuse OCP, and existing 200A fused service disconnect. Existing 200A MLO load center with 200A bus.
Start Date Submittal Complete Date Status  
12/06/2024 RESIDENTIAL SOLAR v.1 01/07/2025 APPROVED Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-RES-1224-07010
Permite Description: Roof mount 8.60kW DC photovoltaic solar system; 20 modules with microinverters, 2 branches, PV combiner Box, Supply Side Tap between 320A Meter, PV system with 40A fuse OCP, and existing 200A fused service disconnect. Existing 200A MLO load center with 200A bus.
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
02/25/2025 BULD - Electrical Clearance N/A Partial Pass Partial for the line-side tap - DGL Clearance was called into TEP at 3:50pm
Pending solar

Completed Inspections

Permit Status: Complete
Permit Number: TC-RES-1224-07010
Permit Description: Roof mount 8.60kW DC photovoltaic solar system; 20 modules with microinverters, 2 branches, PV combiner Box, Supply Side Tap between 320A Meter, PV system with 40A fuse OCP, and existing 200A fused service disconnect. Existing 200A MLO load center with 200A bus.
Total Completed Inspections - 4
Date Description Inspector Results Comments
02/26/2025 COT - RSOL - Electrical Underground Solar Project Passed 2/26/25 pass
02/27/2025 RSBU - Building Final Passed
02/27/2025 COT - RSOL - Electrical Final Solar Project Passed
02/27/2025 BULD - Electrical Clearance Passed Approved solar - DGC Clearance to TEP is required for the solar meter

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-LOEBEL VICKY PV 8.60 KW-DRAWINGS_V1.PDF DOCUMENTS VIEW
LOEBEL VICKY PV 8.60 KW-SPECS_V1.PDF DOCUMENTS VIEW