Permit: TC-RES-1223-10061
Permit Details
Apply Date:
12/13/2023
Applicant:
Andres Amado
Description:
Installation of new Private water service line from the Meter to 10' outside of the house (house Connection) part of Rodeo addition phase 2 TW project. The water line will be a 1-inch pex, buried at 14 inches. 12awg tracer wire will be taped to the pex every ten ft. from the new meter to the tie-in point. The new 5/8 meter will have a 1-inch meter valve installed on the customer's side.
Permit Reviews
Permit Number - TC-RES-1223-10061
Permit Status: Complete
Permit Description: Installation of new Private water service line from the Meter to 10' outside of the house (house Connection) part of Rodeo addition phase 2 TW project. The water line will be a 1-inch pex, buried at 14 inches. 12awg tracer wire will be taped to the pex every ten ft. from the new meter to the tie-in point. The new 5/8 meter will have a 1-inch meter valve installed on the customer's side.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
12/13/2023 | RESIDENTIAL SIMPLE REVIEW v.1 | 12/14/2023 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-RES-1223-10061
Permite Description: Installation of new Private water service line from the Meter to 10' outside of the house (house Connection) part of Rodeo addition phase 2 TW project. The water line will be a 1-inch pex, buried at 14 inches. 12awg tracer wire will be taped to the pex every ten ft. from the new meter to the tie-in point. The new 5/8 meter will have a 1-inch meter valve installed on the customer's side.
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/26/2024 | RSPL - Plumbing Progress | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-1223-10061
Permit Description: Installation of new Private water service line from the Meter to 10' outside of the house (house Connection) part of Rodeo addition phase 2 TW project. The water line will be a 1-inch pex, buried at 14 inches. 12awg tracer wire will be taped to the pex every ten ft. from the new meter to the tie-in point. The new 5/8 meter will have a 1-inch meter valve installed on the customer's side.
Total Completed Inspections - 3
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/26/2024 | COT - RSPL - Yard Water Line | Passed | ||
07/26/2024 | COT - RSPL - Plumbing Final | Passed | Approved 1"PEX yard water line from new meter location to house tie-in, okay to shade and backfill progress areas | |
07/26/2024 | COT - RSPL - Rough Soil | Passed |