Permit: TC-RES-1222-01769
Permit Details
Status:
Inspections Complete
Type:
Residential Building - One or Two Family
Address:
2517 E GLENN ST UNIT 2
Address NEW:
2517 E GLENN ST UNIT 2
Apply Date:
12/28/2022
Applicant:
Chris Kent
Description:
Accessory Dwelling Unit
Permit Reviews
Permit Number - TC-RES-1222-01769
Permit Status: Inspections complete
Permit Description: Accessory Dwelling Unit
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/13/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 02/13/2025 | APPROVED |
| 04/29/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/29/2024 | REQUIRES RESUBMIT |
| 05/15/2023 | RESIDENTIAL NEW DWELLING v.1 | 06/15/2023 | APPROVED |
| 03/17/2023 | RESIDENTIAL NEW DWELLING v.2 | 04/07/2023 | APPROVED |
| 01/30/2023 | RESIDENTIAL NEW DWELLING v.1 | 03/02/2023 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-RES-1222-01769
Permit Status: Inspections complete
Permit Description: Accessory Dwelling Unit
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/22/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-RES-1222-01769
Permit Status: Inspections complete
Permit Description: Accessory Dwelling Unit
| Date | Description | Comments |
|---|---|---|
| 01/30/2023 | Pending zoning approval a separate address may be required. Please contact Pima County Addressing Addressing@pima.gov or 520-724-9512 | |
| 04/26/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 02/02/2023 | A final elevation certificate is required before final inspection | |
| 02/02/2023 | An intermediate elevation certificate of the formed pre-slab is required before the pre-slab/grading inspection | |
| 04/29/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-1222-01769
Permite Description: Accessory Dwelling Unit
Total Outstanding Inspections - 14
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/06/2023 | COT - RSBU - Preslab | N/A | Not Ready | |
| 06/14/2024 | COT - RSEL - Outdoor Lighting | N/A | Not Ready | |
| 07/26/2024 | COT - RSEL - Electrical Final | N/A | Partial Pass | Partial approval for internal wiring on electrical panel at north side of ADU |
| 04/25/2024 | COT - RSPL - Plumbing Final | N/A | Not Ready | |
| 05/22/2024 | BULD - Electrical Clearance | N/A | Not Applicable | |
| 01/28/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 12/21/2023 | COT - RSBU - Interior Shear Bracing | N/A | Not Ready | |
| 06/10/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Not Ready | |
| 01/28/2025 | COT - RSPL - Gas Pressure Test | N/A | Not Applicable | |
| 01/28/2025 | COT - RSPL - Rough Soil | N/A | Not Applicable | |
| 01/28/2025 | COT - RSPL - Sewer | N/A | Not Applicable | |
| 01/31/2025 | RSEL - Electrical Progress | N/A | Not Applicable | |
| 01/31/2025 | RSME - Mechanical Progress | N/A | Not Applicable | |
| 01/31/2025 | RSPL - Plumbing Progress | N/A | Not Applicable |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-1222-01769
Permit Description: Accessory Dwelling Unit
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/17/2023 | COT - RSBU - Preslab | Passed | ||
| 04/01/2024 | COT - RSBU - Roof Nailing | Passed | Duplicate inspection. 4/1/2024 | |
| 01/07/2025 | COT - RSEL - Outdoor Lighting | Passed | ||
| 01/28/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 01/28/2025 | COT - RSEL - Grounding/Bonding | Passed | ||
| 01/28/2025 | COT - RSPL - Plumbing Final | Passed | ||
| 01/28/2025 | COT - RSPL - Yard Water Line | Passed | ||
| 01/31/2025 | RSBU - Building Final | Passed | ||
| 01/31/2025 | COT - RSME - Mechanical Final | Passed |