Permit: TC-RES-1123-09721
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
7745 E CAMINO PERDIDO
Address NEW:
7745 E CAMINO PERDIDO
Apply Date:
11/27/2023
Applicant:
James Watson
Description:
Renovate SFR
Permit Reviews
Permit Number - TC-RES-1123-09721
Permit Status: Complete
Permit Description: Renovate SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/02/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/03/2025 | APPROVED |
| 01/12/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/12/2024 | REQUIRES RESUBMIT |
| 01/17/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/18/2024 | REQUIRES RESUBMIT |
| 03/18/2024 | RESIDENTIAL NEW DWELLING v.1 | 03/19/2024 | REQUIRES RESUBMIT |
| 01/12/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 01/16/2024 | APPROVED |
| 12/01/2023 | RESIDENTIAL NEW DWELLING v.1 | 12/21/2023 | APPROVED |
| 02/09/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 02/12/2024 | APPROVED |
| 03/25/2024 | RESIDENTIAL NEW DWELLING v.2 | 04/25/2024 | APPROVED |
Conditions
Permit Number - TC-RES-1123-09721
Permit Status: Complete
Permit Description: Renovate SFR
| Date | Description | Comments |
|---|---|---|
| 04/09/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 12/13/2023 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 12/13/2023 | Post-Installed Anchor Inspection Report is required. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-RES-1123-09721
Permite Description: Renovate SFR
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/12/2024 | COT - RSEL - Electrical Underground | N/A | Not Applicable | |
| 05/15/2024 | BULD - Electrical Clearance | N/A | Not Applicable | Completed on separate permit; ok to close walls. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-1123-09721
Permit Description: Renovate SFR
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/08/2024 | COT - RSPL - Rough Soil | Passed | ||
| 03/26/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Two wood columns post footing approved. Okay for concrete placement. 3/26/2024 | |
| 03/26/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 04/04/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 06/17/2024 | COT - BULD - SWG Clearance | Passed | ||
| 06/25/2024 | COT - RSPL - Plumbing Final | Passed | ||
| 06/25/2024 | COT - RSME - Mechanical Final | Passed | ||
| 06/25/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 06/25/2024 | COT - RSEL - Electrical Final | Passed | ||
| 06/25/2024 | RSBU - Building Final | Passed |