Permit: TC-RES-1123-09378
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
2023 E 18TH ST
Address NEW:
2023 E 18TH ST
Apply Date:
11/08/2023
Applicant:
Jose Quintero
Description:
SFR
Permit Reviews
Permit Number - TC-RES-1123-09378
Permit Status: Complete
Permit Description: SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/13/2023 | RESIDENTIAL NEW DWELLING v.1 | 12/01/2023 | REQUIRES RESUBMIT |
| 12/12/2023 | RESTAMP - RESIDENTIAL v.1 | 12/13/2023 | APPROVED |
| 05/20/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/21/2024 | APPROVED |
| 12/08/2023 | RESIDENTIAL NEW DWELLING v.2 | 12/12/2023 | APPROVED |
Conditions
Permit Number - TC-RES-1123-09378
Permit Status: Complete
Permit Description: SFR
| Date | Description | Comments |
|---|---|---|
| 11/27/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 11/27/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-RES-1123-09378
Permite Description: SFR
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/22/2023 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Not Ready | |
| 04/12/2024 | COT - RSEL - Electrical Underground | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-1123-09378
Permit Description: SFR
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/20/2023 | COT - RSPL - Rough Soil | Passed | 12/20/23: ok to back fill. | |
| 01/04/2024 | COT - RSBU - Preslab | Passed | Rebar and hold downs per plans. Okay for concrete placement in footings and slab. 1/4/2024 | |
| 01/04/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Rebar and hold downs per plans. Okay for concrete placement in footings and slab. 1/4/2024 | |
| 01/22/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 01/22/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 01/31/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 01/31/2024 | BULD - Electrical Clearance | Passed | ||
| 01/31/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 02/29/2024 | COT - RSPL - Sewer | Passed | Ok to cover sewer line and finish asphalt progress area. | |
| 02/29/2024 | COT - RSPL - Plumbing Final | Passed | Ok to cover progress area. | |
| 04/12/2024 | COT - RSEL - Electrical Final | Passed | ||
| 04/12/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
| 04/12/2024 | COT - RSPL - Yard Water Line | Passed | ||
| 04/18/2024 | COT - RSME - Mechanical Final | Passed | ||
| 04/18/2024 | RSBU - Building Final | Passed |