Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Address NEW:
1920 W PUEBLO VISTA BL
Apply Date:
11/21/2022
Applicant:
Jesus Marquez
Description:
SFR

Permit Reviews

Permit Number - TC-RES-1122-01015
Permit Status: Complete
Permit Description: SFR
Start Date Submittal Complete Date Status  
12/05/2022 RESIDENTIAL NEW DWELLING v.1 12/19/2022 APPROVED Review Details

Conditions

Permit Number - TC-RES-1122-01015
Permit Status: Complete
Permit Description: SFR
Date Description Comments
12/08/2022 A final elevation certificate is needed before final inspection
12/08/2022 An intermediate elevation certificate is needed before pre-slab inspection
12/19/2022 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
05/13/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-RES-1122-01015
Permite Description: SFR
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
01/10/2023 COT - RSPL - Sewer N/A Partial Pass partial approval ok to cover, require HCS connection

Completed Inspections

Permit Status: Complete
Permit Number: TC-RES-1122-01015
Permit Description: SFR
Total Completed Inspections - 19
Date Description Inspector Results Comments
01/10/2023 COT - RSPL - Yard Water Line Passed
01/10/2023 COT - RSPL - Rough Soil Passed
01/19/2023 COT - RSBU - Preslab Passed Ok to place concrete in progress areas.
01/19/2023 COT - RSBU - Excavation/Rebar/Zoning Passed Ok to place concrete in progress areas.
02/07/2023 COT - RSBU - Roof Nailing Passed Ok to dry in roof system.
02/07/2023 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed Ok to cover exterior walls.
06/06/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
06/06/2023 COT - RSEL - Electrical Underground Passed
06/06/2023 COT - RSEL - Grounding/Bonding Passed
06/06/2023 COT - RSPL - Gas Pressure Test Passed
06/06/2023 BULD - Electrical Clearance Passed Clearance for TEP ECO. 6/6/2023
08/20/2024 COT - RSPL - Sewer Passed 8/20/24: HCS connection made per plan. Ok to backfill. Shading required.
09/19/2024 COT - BULD - SWG Clearance Passed Ok to set residential gas meter for new service.
10/01/2024 ENGR Engineering Final Passed
10/01/2024 COT - RSEL - Outdoor Lighting Passed
10/01/2024 COT - RSPL - Plumbing Final Passed
10/02/2024 COT - RSME - Mechanical Final Passed
10/02/2024 RSBU - Building Final Passed
10/02/2024 COT - RSEL - Electrical Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
2_COMMENT RESPONSE LETTER_V1.PDF DOCUMENTS VIEW
CONS-2_PLAN SET_V1.PDF DOCUMENTS VIEW
HVAC MODEL ENERGY MARQUEZ PARCEL 118-05-0540_V1.PDF DOCUMENTS VIEW