Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Address:
2620 N PLUMER AV
Address NEW:
2620 N PLUMER AV
Apply Date:
11/21/2022
Applicant:
TFS Solar
Description:
roof mount 1.5 kW DC addition to existing photovoltaic solar system (new total system size: 10.22 kW), 4 additional DC modules, 1 existing inverter with 2 strings, 60A PV breaker, line side interconnection

Permit Reviews

Permit Number - TC-RES-1122-01011
Permit Status: Complete
Permit Description: roof mount 1.5 kW DC addition to existing photovoltaic solar system (new total system size: 10.22 kW), 4 additional DC modules, 1 existing inverter with 2 strings, 60A PV breaker, line side interconnection
Start Date Submittal Complete Date Status  
11/29/2022 RESIDENTIAL SOLAR v.1 12/30/2022 APPROVED Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-RES-1122-01011
Permite Description: roof mount 1.5 kW DC addition to existing photovoltaic solar system (new total system size: 10.22 kW), 4 additional DC modules, 1 existing inverter with 2 strings, 60A PV breaker, line side interconnection
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
03/23/2023 COT - BULD - SWG Clearance N/A Not Applicable

Completed Inspections

Permit Status: Complete
Permit Number: TC-RES-1122-01011
Permit Description: roof mount 1.5 kW DC addition to existing photovoltaic solar system (new total system size: 10.22 kW), 4 additional DC modules, 1 existing inverter with 2 strings, 60A PV breaker, line side interconnection
Total Completed Inspections - 4
Date Description Inspector Results Comments
03/23/2023 BULD - Electrical Clearance Passed TEP DGC
03/23/2023 RSEL - Electrical Progress Passed
03/23/2023 COT - RSEL - Electrical Final Passed
03/23/2023 RSBU - Building Final Passed