Permit: TC-RES-1122-00240
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
2162 E VIRGINIA ST
Address NEW:
2162 E VIRGINIA ST
Apply Date:
11/01/2022
Applicant:
BRANDY PALCHETTI
Description:
• SYSTEM SIZE: 12775W DC, 10150W AC • MODULES: (35) LONGI GREEN ENERGY TECHNOLOGY CO LTD: LR4-60HPH-365M • INVERTERS: (35) ENPHASE ENERGY: IQ7PLUS-72-2-US • RACKING: SOLLEGA FASTRACK510 WITH 304 STAINLESS STEEL HARDWARE
Permit Reviews
Permit Number - TC-RES-1122-00240
Permit Status: Complete
Permit Description: • SYSTEM SIZE: 12775W DC, 10150W AC
• MODULES: (35) LONGI GREEN ENERGY TECHNOLOGY CO
LTD: LR4-60HPH-365M
• INVERTERS: (35) ENPHASE ENERGY: IQ7PLUS-72-2-US
• RACKING: SOLLEGA FASTRACK510 WITH 304 STAINLESS
STEEL HARDWARE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/04/2022 | RESIDENTIAL SOLAR v.1 | 12/02/2022 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-RES-1122-00240
Permite Description: • SYSTEM SIZE: 12775W DC, 10150W AC
• MODULES: (35) LONGI GREEN ENERGY TECHNOLOGY CO
LTD: LR4-60HPH-365M
• INVERTERS: (35) ENPHASE ENERGY: IQ7PLUS-72-2-US
• RACKING: SOLLEGA FASTRACK510 WITH 304 STAINLESS
STEEL HARDWARE
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/04/2023 | COT - RSEL - Electrical Final | N/A | Canceled | 4/4/23- Cancelled by Field Contact Jacob |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-1122-00240
Permit Description: • SYSTEM SIZE: 12775W DC, 10150W AC
• MODULES: (35) LONGI GREEN ENERGY TECHNOLOGY CO
LTD: LR4-60HPH-365M
• INVERTERS: (35) ENPHASE ENERGY: IQ7PLUS-72-2-US
• RACKING: SOLLEGA FASTRACK510 WITH 304 STAINLESS
STEEL HARDWARE
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/14/2023 | BULD - Electrical Clearance | Passed | 7/14/23: PV Solar panels, converter box, breaker for main panel, and all labeling is installed for solar system. Okay to install meter for solar system in panel box. DGC/DGL Clearance issued. | |
| 07/14/2023 | RSEL - Electrical Progress | Passed | 7/14/23: PV Solar panels, converter box, breaker for main panel, and all labeling is installed for solar system. Okay to install meter for solar system in panel box. DGC/DGL Clearance issued. | |
| 07/14/2023 | COT - RSEL - Electrical Final | Passed | 7/14/23: PV Solar panels, converter box, breaker for main panel, and all labeling is installed for solar system. Okay to install meter for solar system in panel box. DGC/DGL Clearance issued. | |
| 07/14/2023 | RSBU - Building Final | Passed | 7/14/23: PV Solar panels, converter box, breaker for main panel, and all labeling is installed for solar system. Okay to install meter for solar system in panel box. DGC/DGL Clearance issued. |