Permit: TC-RES-1024-06239
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
2308 E WARWICK VISTA
Address NEW:
2308 E WARWICK VISTA
Apply Date:
10/28/2024
Applicant:
Mackenzie Glenn
Description:
Install 8.40 kW roof-mounted PV system with electrical service upgrade to new 225A main service panel with new 200aA main breaker.
Permit Reviews
Permit Number - TC-RES-1024-06239
Permit Status: Complete
Permit Description: Install 8.40 kW roof-mounted PV system with electrical service upgrade to new 225A main service panel with new 200aA main breaker.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/29/2024 | RESIDENTIAL SOLAR v.1 | 11/27/2024 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-RES-1024-06239
Permite Description: Install 8.40 kW roof-mounted PV system with electrical service upgrade to new 225A main service panel with new 200aA main breaker.
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/17/2025 | BULD - Electrical Clearance | N/A | Partial Pass | partial for MPU |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-1024-06239
Permit Description: Install 8.40 kW roof-mounted PV system with electrical service upgrade to new 225A main service panel with new 200aA main breaker.
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/17/2025 | COT - RSOL - Electrical Underground Solar Project | Passed | from new pedestal location to MPU | |
| 10/17/2025 | COT - RSOL - Grounding/Bonding Solar Project | Passed | Passed solar final 10/17/25 CLEARANCE DGC | |
| 10/17/2025 | RSBU - Building Final | Passed | Passed solar final 10/17/25 CLEARANCE DGC | |
| 10/17/2025 | COT - RSOL - Electrical Final Solar Project | Passed | Passed solar final 10/17/25 CLEARANCE DGC | |
| 10/17/2025 | BULD - Electrical Clearance | Passed | Passed solar final 10/17/25 CLEARANCE DGC |