Residential Building - One or Two Family
Apply Date:
10/28/2024
Applicant:
Gregory Chaisson
Description:
200 amp all in one overhead upgrade with new grounding rods and bonding the water/gas lines. Then remove the 100 amp existing loadcenter in the pantry closet to a 12 in x 12 in nema 1 jbox. Run 1.25 in emt about 30 ft from the 200a main to the nema1 jbox. Run the circuits back to the main panel, then install correct sized breakers. Remove small fuse box inside the furnace closet and install an 8in x 8in nema 1 jbox, run 3/4 in emt from the jbox to the main 200a panel. Run 3 circuits back to the main panel, install the correct sized breakers for those circuits. Make up both splice jboxes. Label the main panel.

Permit Reviews

Permit Number - TC-RES-1024-06238
Permit Status: Inspections
Permit Description: 200 amp all in one overhead upgrade with new grounding rods and bonding the water/gas lines. Then remove the 100 amp existing loadcenter in the pantry closet to a 12 in x 12 in nema 1 jbox. Run 1.25 in emt about 30 ft from the 200a main to the nema1 jbox. Run the circuits back to the main panel, then install correct sized breakers. Remove small fuse box inside the furnace closet and install an 8in x 8in nema 1 jbox, run 3/4 in emt from the jbox to the main 200a panel. Run 3 circuits back to the main panel, install the correct sized breakers for those circuits. Make up both splice jboxes. Label the main panel.
Start Date Submittal Complete Date Status  
10/29/2024 RESIDENTIAL SIMPLE REVIEW v.2 10/30/2024 APPROVED Review Details
10/28/2024 RESIDENTIAL SIMPLE REVIEW v.1 10/28/2024 REQUIRES RESUBMIT Review Details

Completed Inspections

Permit Status: Inspections
Permit Number: TC-RES-1024-06238
Permit Description: 200 amp all in one overhead upgrade with new grounding rods and bonding the water/gas lines. Then remove the 100 amp existing loadcenter in the pantry closet to a 12 in x 12 in nema 1 jbox. Run 1.25 in emt about 30 ft from the 200a main to the nema1 jbox. Run the circuits back to the main panel, then install correct sized breakers. Remove small fuse box inside the furnace closet and install an 8in x 8in nema 1 jbox, run 3/4 in emt from the jbox to the main 200a panel. Run 3 circuits back to the main panel, install the correct sized breakers for those circuits. Make up both splice jboxes. Label the main panel.
Total Completed Inspections - 2
Date Description Inspector Results Comments
12/04/2024 BULD - Electrical Clearance Passed Approved 200A service panel upgrade - INCR Clearance was called into TEPt 11:50am
Pending final
12/05/2024 COT - RSEL - Electrical Final Passed Passed final 12/5/24 CLEARANCE INCR

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW