Permit: TC-RES-1022-00107
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
1550 N YAVAPAI ST UNIT 1
Address NEW:
1550 N YAVAPAI ST UNIT 1
Apply Date:
03/03/2022
Applicant:
Ramon VALDEZ
Description:
DUPLEX DUPLVAL82 T22-M0037
Permit Reviews
Permit Number - TC-RES-1022-00107
Permit Status: Complete
Permit Description: DUPLEX DUPLVAL82 T22-M0037
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/07/2022 | RESIDENTIAL NEW DWELLING v.1 | 12/12/2022 | APPROVED |
| 12/12/2022 | RESIDENTIAL NEW DWELLING v.1 | 12/12/2022 | APPROVED |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-1022-00107
Permit Description: DUPLEX DUPLVAL82 T22-M0037
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/15/2022 | COT - RSPL - Rough Soil | Passed | okay to backfill. | |
| 12/15/2022 | COT - RSPL - Sewer | Passed | okay to backfill. | |
| 12/19/2022 | COT - RSBU - Preslab | Passed | okay for concrete. | |
| 12/19/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | okay for concrete in footings. | |
| 12/19/2022 | COT - RSEL - Grounding/Bonding | Passed | UFER is in place. | |
| 12/30/2022 | COT - RSPL - Yard Water Line | Passed | ||
| 01/23/2023 | RSBU - Building Progress | Passed | firewall/fire barrier between units is 5/8” type X drywall properly nailed off floor to bottom of roof deck. Joints are being taped and mudded. | |
| 01/23/2023 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | H2.5 clips are installed and properly nailed to the top plate and trusses. | |
| 01/23/2023 | COT - RSBU - Roof Nailing | Passed | roof nailing is good. okay to dry-in roof. | |
| 01/26/2023 | BULD - Electrical Clearance | Passed | clearance for TEP ECO. Botha unit 1 and 2. | |
| 01/26/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 01/26/2023 | COT - RSEL - Temporary Service | Passed | clearance for TEP ECO. Both unit 1 and 2. | |
| 03/01/2023 | COT - RSEL - Electrical Final | Passed | Inspection is for Units #1 & #2. | |
| 03/01/2023 | COT - RSEL - Outdoor Lighting | Passed | Inspection is for Units #1 & #2. | |
| 03/01/2023 | RSBU - Building Final | Passed | Inspection is for Units #1 & #2. | |
| 03/01/2023 | COT - RSME - Mechanical Final | Passed | Inspection is for Units #1 & #2 | |
| 03/01/2023 | COT - RSPL - Plumbing Final | Passed | Inspection is for units #1 and #2 | |
| 03/01/2023 | ENGR Engineering Final | Passed |