Permit: TC-RES-0924-05382
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
5669 E FORT LOWELL RD
Address NEW:
5669 E FORT LOWELL RD
Apply Date:
09/17/2024
Applicant:
TFS Solar
Description:
Roof mount 15.99 kW DC photovoltaic solar system; 39 modules; 41 kWh Storage, 3 Tesla Powerwall-3 batteries with integrated PV inverter with 2 string each on two Powerwall-3s and 1 string on another Powerwall-3; Tesla Gateway; 200A bus load center with 200A MCB
Permit Reviews
Permit Number - TC-RES-0924-05382
Permit Status: Complete
Permit Description: Roof mount 15.99 kW DC photovoltaic solar system; 39 modules; 41 kWh Storage, 3 Tesla Powerwall-3 batteries with integrated PV inverter with 2 string each on two Powerwall-3s and 1 string on another Powerwall-3; Tesla Gateway; 200A bus load center with 200A MCB
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/11/2024 | RESIDENTIAL SOLAR v.2 | 01/13/2025 | APPROVED |
| 04/22/2025 | RESIDENTIAL SOLAR REVISION v.1 | 05/28/2025 | APPROVED |
| 03/03/2025 | RESIDENTIAL SOLAR REVISION v.1 | 04/01/2025 | APPROVED |
| 01/13/2025 | RESTAMP - RESIDENTIAL v.1 | 01/13/2025 | APPROVED |
| 09/18/2024 | RESIDENTIAL SOLAR v.1 | 10/17/2024 | REQUIRES RESUBMIT |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0924-05382
Permit Description: Roof mount 15.99 kW DC photovoltaic solar system; 39 modules; 41 kWh Storage, 3 Tesla Powerwall-3 batteries with integrated PV inverter with 2 string each on two Powerwall-3s and 1 string on another Powerwall-3; Tesla Gateway; 200A bus load center with 200A MCB
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/29/2025 | RSBU - Building Final | Passed | Installed per stamped plans 5/29/25 CLEARANCE DGC/BAT | |
| 05/29/2025 | COT - RSOL - Electrical Progress Solar Project | Passed | Installed per stamped plans 5/29/25 CLEARANCE DGC/BAT | |
| 05/29/2025 | COT - RSOL - Grounding/Bonding Solar Project | Passed | Installed per stamped plans 5/29/25 CLEARANCE DGC/BAT | |
| 05/29/2025 | BULD - Electrical Clearance | Passed | Installed per stamped plans 5/29/25 CLEARANCE DGC/BAT |