Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-RES-0923-07881
Permit Details
Apply Date:
09/08/2023
Applicant:
TFS Solar
Description:
roof mount 2.1 kW DC addition to existing photovoltaic solar system (new total system size: 4.75 kW), 5 additional modules, 1 additional branch circuit, PV subpanel, interconnection via meter socket adapter to 125A bus with 125A MCB
Permit Reviews
Permit Number - TC-RES-0923-07881
Permit Status: Inspections complete
Permit Description: roof mount 2.1 kW DC addition to existing photovoltaic solar system (new total system size: 4.75 kW), 5 additional modules, 1 additional branch circuit, PV subpanel, interconnection via meter socket adapter to 125A bus with 125A MCB
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/11/2023 | RESIDENTIAL SOLAR v.1 | 10/03/2023 | APPROVED |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-0923-07881
Permit Description: roof mount 2.1 kW DC addition to existing photovoltaic solar system (new total system size: 4.75 kW), 5 additional modules, 1 additional branch circuit, PV subpanel, interconnection via meter socket adapter to 125A bus with 125A MCB
Total Completed Inspections - 3
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/11/2024 | RSBU - Building Final | Passed | ||
01/11/2024 | COT - RSOL - Electrical Final Solar Project | Passed | ||
01/11/2024 | BULD - Electrical Clearance | Passed | Approved, DGC/DGL Clearance to TEP is required for the solar meter |