Permit Details

Status:
In Review
Type:
Residential Building - One or Two Family
Apply Date:
09/05/2023
Applicant:
alex enoch
Description:
SFR

Permit Reviews

Permit Number - TC-RES-0923-07783
Permit Status: In review
Permit Description: SFR
Start Date Submittal Complete Date Status  
11/16/2023 RESTAMP - RESIDENTIAL v.1 11/16/2023 APPROVED Review Details
10/31/2023 RESIDENTIAL NEW DWELLING v.2 11/16/2023 APPROVED Review Details
09/05/2023 RESIDENTIAL NEW DWELLING v.1 09/29/2023 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-RES-0923-07783
Permit Status: In review
Permit Description: SFR
Date Description Comments
11/16/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: In Review
Permit Number: TC-RES-0923-07783
Permite Description: SFR
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
12/18/2023 COT - RSBU - Excavation/Rebar/Zoning N/A Re-inspection required 12/18/23: footing reinforcements for column S3.0/3 calls for #4 rebar spaced at 8" O.C. Each way. (Min 3). All footings reinforcement over spaced.
12/18/2023 COT - RSBU - Preslab N/A Re-inspection required 12/18/23: footing reinforcements for column S3.0/3 calls for #4 rebar spaced at 8" O.C. Each way. (Min 3). All footings reinforcement over spaced.

Completed Inspections

Permit Status: In Review
Permit Number: TC-RES-0923-07783
Permit Description: SFR
Total Completed Inspections - 16
Date Description Inspector Results Comments
12/19/2023 COT - RSBU - Excavation/Rebar/Zoning Passed
12/19/2023 COT - RSBU - Preslab Passed
01/03/2024 COT - RSEL - Electrical Underground Passed Electrical conduit is ran from Unit #1 to Unit #2. Unit #1 will have 2 electrical meters installed on the north side once exterior framing is complete. Okay to backfill electrical trench.
01/03/2024 COT - RSPL - Rough Soil Passed Underground plumbing is connected to main sewer line, with green tracer wire installed around pipe. Okay to shade pipes and backfill trenches.
01/03/2024 COT - RSPL - Sewer Passed Underground plumbing is connected to main sewer line, with green tracer wire installed around pipe. Okay to shade pipes and backfill trenches.
01/03/2024 COT - RSPL - Yard Water Line Passed Water line for both Units 1 & 2 are connected to one meter at this time, with blue tracer wire on each main water supply line. Okay to shade pipes and backfill trenches.
01/30/2024 BULD - Electrical Clearance Passed Approved new 200A service panel, ECO Clearance to TEP is required for the construction power at unit #2
03/05/2024 COT - RSBU - Exterior Clips/Sheathing Passed Ok to cover exterior walls.
03/05/2024 COT - RSBU - Roof Nailing Passed Ok to dry-in roof system.
04/04/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Ok to insulate and cover wall.
04/04/2024 COT - RSEL - Grounding/Bonding Passed
08/15/2024 COT - RSEL - Outdoor Lighting Passed
08/28/2024 RSBU - Building Final Passed
08/28/2024 COT - RSEL - Electrical Final Passed
08/28/2024 COT - RSME - Mechanical Final Passed
08/28/2024 COT - RSPL - Plumbing Final Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-PLANS SUB2_V2.PDF DOCUMENTS VIEW