Permit: TC-RES-0825-03844
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
2833 E 2ND ST
Address NEW:
2833 E 2ND ST
Apply Date:
08/05/2025
Applicant:
TFS Solar
Description:
REV_1 Roof mount 6.9 kW DC addition to existing photovoltaic solar system (new total system size: 11.61 kW), 16 additional AC modules (2 branches) to PV combiner box. NEW 125A PV subpanel to combine all outputs. Relocate PV meter and disconnect to main service area on ADU. Interconnection via 60A meter socket adapter. 200A bus with 200A MCB.
Permit Reviews
Permit Number - TC-RES-0825-03844
Permit Status: Complete
Permit Description: REV_1 Roof mount 6.9 kW DC addition to existing photovoltaic solar system (new total system size: 11.61 kW), 16 additional AC modules (2 branches) to PV combiner box. NEW 125A PV subpanel to combine all outputs. Relocate PV meter and disconnect to main service area on ADU.
Interconnection via 60A meter socket adapter. 200A bus with 200A MCB.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/10/2025 | RESIDENTIAL SOLAR REVISION v.1 | 09/29/2025 | APPROVED |
| 08/05/2025 | RESIDENTIAL SOLAR v.1 | 09/02/2025 | APPROVED |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0825-03844
Permit Description: REV_1 Roof mount 6.9 kW DC addition to existing photovoltaic solar system (new total system size: 11.61 kW), 16 additional AC modules (2 branches) to PV combiner box. NEW 125A PV subpanel to combine all outputs. Relocate PV meter and disconnect to main service area on ADU.
Interconnection via 60A meter socket adapter. 200A bus with 200A MCB.
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/23/2025 | RSBU - Building Final | Passed | ||
| 10/23/2025 | COT - RSOL - Electrical Final Solar Project | Passed | ||
| 10/23/2025 | BULD - Electrical Clearance | Passed | Clearance to TEP DGC/DGL. 10/23/2025 |