Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-RES-0824-04885
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
835 W CALLE ANTONIA
Address NEW:
835 W CALLE ANTONIA
Apply Date:
08/21/2024
Applicant:
Project Manager
Description:
Installation of a 10.665kw dc system/MSA
Permit Reviews
Permit Number - TC-RES-0824-04885
Permit Status: Complete
Permit Description: Installation of a 10.665kw dc system/MSA
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/21/2024 | RESIDENTIAL SOLAR REVISION v.1 | 12/09/2024 | APPROVED |
| 09/22/2024 | RESIDENTIAL SOLAR v.1 | 09/23/2024 | REQUIRES RESUBMIT |
| 11/12/2024 | RESIDENTIAL SOLAR v.2 | 11/13/2024 | APPROVED |
Conditions
Permit Number - TC-RES-0824-04885
Permit Status: Complete
Permit Description: Installation of a 10.665kw dc system/MSA
| Date | Description | Comments |
|---|---|---|
| 11/12/2024 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0824-04885
Permit Description: Installation of a 10.665kw dc system/MSA
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/20/2025 | BULD - Electrical Clearance | Passed | 20 FEB 25 TEP CLEARANCE: DGC |
|
| 02/20/2025 | RSBU - Building Final | Passed | ||
| 02/20/2025 | COT - RSOL - Grounding/Bonding Solar Project | Passed | ||
| 02/20/2025 | COT - RSOL - Electrical Final Solar Project | Passed |