Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Address:
8772 E 3RD ST
Address NEW:
8772 E 3RD ST
Apply Date:
07/09/2025
Applicant:
TFS Solar
Description:
27 kWh Storage addition to existing PV Solar system. 2 Tesla Powerwall-3 batteries added to existing PV system. 200A bus with downsized 175A MCB, interconnection via PCS for battery system, Tesla Backup Switch for whole home backup.

Permit Reviews

Permit Number - TC-RES-0725-03427
Permit Status: Complete
Permit Description: 27 kWh Storage addition to existing PV Solar system. 2 Tesla Powerwall-3 batteries added to existing PV system. 200A bus with downsized 175A MCB, interconnection via PCS for battery system, Tesla Backup Switch for whole home backup.
Start Date Submittal Complete Date Status  
07/09/2025 RESIDENTIAL SOLAR v.1 08/06/2025 APPROVED Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-RES-0725-03427
Permite Description: 27 kWh Storage addition to existing PV Solar system. 2 Tesla Powerwall-3 batteries added to existing PV system. 200A bus with downsized 175A MCB, interconnection via PCS for battery system, Tesla Backup Switch for whole home backup.
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
09/22/2025 BULD - Electrical Clearance N/A Partial Pass Partial for the Tesla meter switch and 175A derate - DGL Clearance was called into TEP at 10:15 am
Pending solar final

Completed Inspections

Permit Status: Complete
Permit Number: TC-RES-0725-03427
Permit Description: 27 kWh Storage addition to existing PV Solar system. 2 Tesla Powerwall-3 batteries added to existing PV system. 200A bus with downsized 175A MCB, interconnection via PCS for battery system, Tesla Backup Switch for whole home backup.
Total Completed Inspections - 3
Date Description Inspector Results Comments
09/24/2025 RSBU - Building Final Passed
09/24/2025 COT - RSOL - Electrical Final Solar Project Passed Approved (2) PW3 battery storage for existing solar - BAT Clearance to TEP is required
09/24/2025 BULD - Electrical Clearance Passed Approved (2) PW3 battery storage for existing solar - BAT Clearance to TEP is required

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-COPLER DON STORAGE 27 KWH-DRAWINGS_V1.PDF DOCUMENTS VIEW
COPLER DON STORAGE 27 KWH-SPECS_V1.PDF DOCUMENTS VIEW