Permit: TC-RES-0724-04427
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
10040 E WATSON DR
Address NEW:
10040 E WATSON DR
Apply Date:
07/30/2024
Applicant:
TFS Solar
Description:
Roof mount 6.88kW DC photovoltaic solar system; 16 modules; 27kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings, 60A breaker; 125A bus with 125A MCB, interconnection via PCS, Tesla Backup Switch
Permit Reviews
Permit Number - TC-RES-0724-04427
Permit Status: Complete
Permit Description: Roof mount 6.88kW DC photovoltaic solar system; 16 modules; 27kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings, 60A breaker; 125A bus with 125A MCB, interconnection via PCS, Tesla Backup Switch
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/29/2024 | RESIDENTIAL SOLAR v.2 | 08/29/2024 | APPROVED |
| 07/31/2024 | RESIDENTIAL SOLAR v.1 | 08/29/2024 | REQUIRES RESUBMIT |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0724-04427
Permit Description: Roof mount 6.88kW DC photovoltaic solar system; 16 modules; 27kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings, 60A breaker; 125A bus with 125A MCB, interconnection via PCS, Tesla Backup Switch
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/23/2024 | RSBU - Building Final | Passed | ||
| 09/23/2024 | COT - RSOL - Electrical Final Solar Project | Passed | Approved solar and battery - DGC/BAT Clearance to TEP is required for the solar meter and battery | |
| 09/23/2024 | BULD - Electrical Clearance | Passed | Approved solar and battery - DGC/BAT Clearance to TEP is required for the solar meter and battery |