Permit: TC-RES-0724-04032
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
826 W CALLE RETAMA
Address NEW:
826 W CALLE RETAMA
Apply Date:
07/10/2024
Applicant:
Anthony Duplantis
Description:
Install 35 roof mounted PV panels, 14.35 kW REV1: Revised as-built-plans to show changes made to the layout. REV2: Derate the main breaker to 150 amps to facilitate the 70 amp interconnection
Permit Reviews
Permit Number - TC-RES-0724-04032
Permit Status: Complete
Permit Description: Install 35 roof mounted PV panels, 14.35 kW
REV1: Revised as-built-plans to show changes made to the layout.
REV2: Derate the main breaker to 150 amps to facilitate the 70 amp interconnection
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/16/2024 | RESIDENTIAL SOLAR v.1 | 01/02/2025 | APPROVED |
| 06/24/2025 | RESIDENTIAL SOLAR REVISION v.2 | 07/03/2025 | APPROVED |
| 11/26/2024 | RESIDENTIAL SOLAR v.2 | 11/26/2024 | REQUIRES RESUBMIT |
| 07/10/2024 | RESIDENTIAL SOLAR v.1 | 08/09/2024 | REQUIRES RESUBMIT |
| 12/02/2024 | RESIDENTIAL SOLAR v.3 | 12/04/2024 | APPROVED |
| 01/09/2025 | RESIDENTIAL SOLAR REVISION v.1 | 01/23/2025 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-RES-0724-04032
Permite Description: Install 35 roof mounted PV panels, 14.35 kW
REV1: Revised as-built-plans to show changes made to the layout.
REV2: Derate the main breaker to 150 amps to facilitate the 70 amp interconnection
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/07/2025 | RSBU - Building Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0724-04032
Permit Description: Install 35 roof mounted PV panels, 14.35 kW
REV1: Revised as-built-plans to show changes made to the layout.
REV2: Derate the main breaker to 150 amps to facilitate the 70 amp interconnection
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/17/2025 | RSBU - Building Final | Passed | Approved solar and battery with 150A derate - DGC/BAT Clearance to TEP is required for the solar meter | |
| 07/17/2025 | COT - RSOL - Electrical Final Solar Project | Passed | ||
| 07/17/2025 | BULD - Electrical Clearance | Passed | Approved solar and battery with 150A derate - DGC/BAT Clearance to TEP is required for the solar meter |