Permit: TC-RES-0724-03943
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
922 S 4TH AV
Address NEW:
922 S 4TH AV
Apply Date:
07/04/2024
Applicant:
TFS Solar
Description:
Roof mount 6.45kW DC photovoltaic solar system; 15 modules; 14 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings, 60A breaker; 225A bus with 200A MCB, Tesla Backup Switch. REV 1: Relocated SES and PV related equipment. Added a Tesla battery expansion pack. 11.5kWh Storage. REV2: Removed Powerwall-3 Expansion Unit from scope of work. (future battery expansion).
Permit Reviews
Permit Number - TC-RES-0724-03943
Permit Status: Issued
Permit Description: Roof mount 6.45kW DC photovoltaic solar system; 15 modules; 14 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings, 60A breaker; 225A bus with 200A MCB, Tesla Backup Switch.
REV 1: Relocated SES and PV related equipment. Added a Tesla battery expansion pack. 11.5kWh Storage.
REV2: Removed Powerwall-3 Expansion Unit from scope of work. (future battery expansion).
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/06/2025 | RESIDENTIAL SOLAR REVISION v.1 | 03/12/2025 | APPROVED |
| 10/31/2024 | RESIDENTIAL SOLAR v.1 | 11/27/2024 | APPROVED |
| 07/08/2024 | RESIDENTIAL SOLAR v.1 | 08/07/2024 | APPROVED |
Completed Inspections
Permit Status: Issued
Permit Number: TC-RES-0724-03943
Permit Description: Roof mount 6.45kW DC photovoltaic solar system; 15 modules; 14 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings, 60A breaker; 225A bus with 200A MCB, Tesla Backup Switch.
REV 1: Relocated SES and PV related equipment. Added a Tesla battery expansion pack. 11.5kWh Storage.
REV2: Removed Powerwall-3 Expansion Unit from scope of work. (future battery expansion).
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/27/2025 | COT - RSOL - Electrical Underground Solar Project | Passed | Approved underground solar and electrical conduits from equipment and service location to the home, okay to backfill progress areas | |
| 02/20/2025 | COT - RSOL - Grounding/Bonding Solar Project | Passed | ||
| 02/20/2025 | RSBU - Building Final | Passed | ||
| 02/20/2025 | COT - RSOL - Electrical Final Solar Project | Passed | ||
| 02/20/2025 | BULD - Electrical Clearance | Passed | Approved solar with powerwall 3 - DGC/BAT clearance to TEP is required for the solar meter |