Permit: TC-RES-0723-06509
Permit Details
Apply Date:
07/13/2023
Applicant:
jose ceja
Description:
SFR
Permit Reviews
Permit Number - TC-RES-0723-06509
Permit Status: Complete
Permit Description: SFR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/13/2023 | RESIDENTIAL NEW DWELLING v.1 | 07/28/2023 | REQUIRES RESUBMIT |
08/25/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 08/28/2023 | APPROVED |
08/01/2023 | RESIDENTIAL NEW DWELLING v.2 | 08/02/2023 | APPROVED |
10/03/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/03/2023 | APPROVED |
Conditions
Permit Number - TC-RES-0723-06509
Permit Status: Complete
Permit Description: SFR
Date | Description | Comments |
---|---|---|
08/02/2023 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as a contact. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
10/03/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
07/27/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
07/27/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0723-06509
Permit Description: SFR
Total Completed Inspections - 19
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/25/2023 | COT - RSPL - Rough Soil | Passed | ||
08/29/2023 | COT - RSEL - Grounding/Bonding | Passed | ||
08/29/2023 | COT - RSBU - Preslab | Passed | ||
08/29/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
09/27/2023 | COT - RSBU - Roof Nailing | Passed | 9/27/23: okay to dry in roof nailing is good | |
09/27/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | 9/27/23: clips and sheathing good okay to proceed to intermediates | |
10/16/2023 | COT - RSEL - Electrical Underground | Passed | ||
10/16/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Mechanical, electrical, and plumbing rough-in is complete. Okay to insulate exterior walls and drywall all walls and ceiling. | |
10/16/2023 | COT - RSBU - Interior Shear Bracing | Passed | 10-16-23: 2-Interior shear walls are framed, plywood sheathing is properly attached. Okay to proceed with drywall application. | |
10/16/2023 | COT - RSPL - Gas Pressure Test | Passed | Gas line is holding 15# of compressed air. Okay to install meter when ready. | |
10/16/2023 | COT - RSPL - Sewer | Passed | Sewer line is connected to main sewer line at street. | |
10/16/2023 | COT - RSPL - Yard Water Line | Passed | Water line is connected to the main water meter. | |
10/16/2023 | COT - BULD - SWG Clearance | Passed | Gas line is holding 15# of compressed air. Okay to install gas meter when ready. | |
10/16/2023 | BULD - Electrical Clearance | Passed | Duplicate inspection. Passed by S Carrazco on 9/17/23 | |
01/03/2024 | RSBU - Building Final | Passed | ||
01/03/2024 | COT - RSEL - Electrical Final | Passed | ||
01/03/2024 | COT - RSEL - Outdoor Lighting | Passed | ||
01/03/2024 | COT - RSME - Mechanical Final | Passed | ||
01/03/2024 | COT - RSPL - Plumbing Final | Passed |