Permit: TC-RES-0723-06272
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
7052 E 3RD ST
Address NEW:
7052 E 3RD ST
Apply Date:
07/03/2023
Applicant:
TFS Solar
Description:
roof mount 4.51 kW DC photovoltaic solar system; 11 AC modules, 1 branches, 20A PV breaker line side interconnection, additional 125A Subpanel
Permit Reviews
Permit Number - TC-RES-0723-06272
Permit Status: Complete
Permit Description: roof mount 4.51 kW DC photovoltaic solar system; 11 AC modules, 1 branches, 20A PV breaker line side interconnection, additional 125A Subpanel
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/06/2023 | RESIDENTIAL SOLAR v.1 | 07/17/2023 | APPROVED |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0723-06272
Permit Description: roof mount 4.51 kW DC photovoltaic solar system; 11 AC modules, 1 branches, 20A PV breaker line side interconnection, additional 125A Subpanel
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/05/2023 | RSBU - Building Final | Passed | ||
| 09/05/2023 | BULD - Electrical Clearance | Passed | Approved, DGC Clearance to TEP is required for the solar meter | |
| 09/05/2023 | COT - RSOL - Electrical Final Solar Project | Passed |