Permit: TC-RES-0626-03531
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
1512 W ARGYLE AV
Address NEW:
1512 W ARGYLE AV
Apply Date:
06/29/2026
Applicant:
TFS Solar
Description:
Roof mount 10.56kW DC photovoltaic solar system; 24 modules with microinverters. 20kWh Storage, 2 Enphase 10C batteries. IQ combiner for PV and Batteries. 200A bus with 200A MCB, interconnection via PCS, Enphase Meter Collar for whole home backup.
Permit Reviews
Permit Number - TC-RES-0626-03531
Permit Status: Complete
Permit Description: Roof mount 10.56kW DC photovoltaic solar system; 24 modules with microinverters. 20kWh Storage, 2 Enphase 10C batteries. IQ combiner for PV and Batteries. 200A bus with 200A MCB, interconnection via PCS, Enphase Meter Collar for whole home backup.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/29/2026 | RESIDENTIAL SOLAR v.1 | 07/02/2026 | APPROVED |
Conditions
Permit Number - TC-RES-0626-03531
Permit Status: Complete
Permit Description: Roof mount 10.56kW DC photovoltaic solar system; 24 modules with microinverters. 20kWh Storage, 2 Enphase 10C batteries. IQ combiner for PV and Batteries. 200A bus with 200A MCB, interconnection via PCS, Enphase Meter Collar for whole home backup.
| Date | Description | Comments |
|---|---|---|
| 07/02/2026 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0626-03531
Permit Description: Roof mount 10.56kW DC photovoltaic solar system; 24 modules with microinverters. 20kWh Storage, 2 Enphase 10C batteries. IQ combiner for PV and Batteries. 200A bus with 200A MCB, interconnection via PCS, Enphase Meter Collar for whole home backup.
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/22/2026 | BULD - Electrical Clearance | Passed | ||
| 09/22/2026 | COT - RSOL - Electrical Final Solar Project | Passed | ||
| 09/22/2026 | RSBU - Building Final | Passed |