Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Address:
5656 E 28TH ST
Address NEW:
5656 E 28TH ST
Apply Date:
06/03/2026
Applicant:
Stephen Jobe
Description:
- access kitchen area - drill a hole towards roof on opposite wall of kitchen stove - run all new 1” black iron pipe upon towards roof - run all new 3/4” and 1/2 black iron pipe - install proper roof jack and apply Henry’s roof coating - install all new 1/2” gas valve - reconnect new line with water heater line -all piping on roof will be mounted Utilizing red block and straps. -upon completion of install, we will perform a 15 pound gas pressure test for 30 minutes to ensure proper hold of pressure -upon pass test, we will leave line pressurized with air and finalize permitting process and schedule inspections. Upon completion of inspections Southwest gas will re-hook up gas meter to system.

Permit Reviews

Permit Number - TC-RES-0626-02968
Permit Status: Complete
Permit Description: - access kitchen area - drill a hole towards roof on opposite wall of kitchen stove - run all new 1” black iron pipe upon towards roof - run all new 3/4” and 1/2 black iron pipe - install proper roof jack and apply Henry’s roof coating - install all new 1/2” gas valve - reconnect new line with water heater line -all piping on roof will be mounted Utilizing red block and straps. -upon completion of install, we will perform a 15 pound gas pressure test for 30 minutes to ensure proper hold of pressure -upon pass test, we will leave line pressurized with air and finalize permitting process and schedule inspections. Upon completion of inspections Southwest gas will re-hook up gas meter to system.
Start Date Submittal Complete Date Status  
06/04/2026 RESIDENTIAL SIMPLE REVIEW v.1 06/04/2026 APPROVED Review Details

Conditions

Permit Number - TC-RES-0626-02968
Permit Status: Complete
Permit Description: - access kitchen area - drill a hole towards roof on opposite wall of kitchen stove - run all new 1” black iron pipe upon towards roof - run all new 3/4” and 1/2 black iron pipe - install proper roof jack and apply Henry’s roof coating - install all new 1/2” gas valve - reconnect new line with water heater line -all piping on roof will be mounted Utilizing red block and straps. -upon completion of install, we will perform a 15 pound gas pressure test for 30 minutes to ensure proper hold of pressure -upon pass test, we will leave line pressurized with air and finalize permitting process and schedule inspections. Upon completion of inspections Southwest gas will re-hook up gas meter to system.
Date Description Comments
06/04/2026 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.

Completed Inspections

Permit Status: Complete
Permit Number: TC-RES-0626-02968
Permit Description: - access kitchen area - drill a hole towards roof on opposite wall of kitchen stove - run all new 1” black iron pipe upon towards roof - run all new 3/4” and 1/2 black iron pipe - install proper roof jack and apply Henry’s roof coating - install all new 1/2” gas valve - reconnect new line with water heater line -all piping on roof will be mounted Utilizing red block and straps. -upon completion of install, we will perform a 15 pound gas pressure test for 30 minutes to ensure proper hold of pressure -upon pass test, we will leave line pressurized with air and finalize permitting process and schedule inspections. Upon completion of inspections Southwest gas will re-hook up gas meter to system.
Total Completed Inspections - 3
Date Description Inspector Results Comments
06/08/2026 COT - BULD - SWG Clearance Passed 06/08/2026
Approved clearance for SWG.
06/08/2026 COT - RSPL - Plumbing Final Passed 06/08/2026
1" and 3/4" BI line run from meter along wall to roof and drop into fixtures - holding under test.
06/08/2026 RSBU - Building Final Passed

Documents

File Name Document Type  
5656 E 28TH_V1.PDF DOCUMENTS VIEW