Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
Inspections
Type:
Residential Building - One or Two Family
Apply Date:
06/12/2025
Applicant:
Marytine Ramos
Description:
REV_1, Equipment Relocation + Trenching; House 2- Installation of a 6.56kw PV System with Battery and 225A MPU

Permit Reviews

Permit Number - TC-RES-0625-02995
Permit Status: Inspections
Permit Description: REV_1, Equipment Relocation + Trenching; House 2- Installation of a 6.56kw PV System with Battery and 225A MPU
Start Date Submittal Complete Date Status  
08/11/2025 RESIDENTIAL SOLAR v.3 08/11/2025 APPROVED Review Details
06/12/2025 RESIDENTIAL SOLAR v.1 08/06/2025 REQUIRES RESUBMIT Review Details
08/11/2025 RESTAMP - RESIDENTIAL v.1 08/12/2025 APPROVED Review Details
04/07/2026 RESIDENTIAL SOLAR REVISION v.2 04/09/2026 APPROVED Review Details
03/20/2026 RESIDENTIAL SOLAR REVISION v.1 04/06/2026 REQUIRES RESUBMIT Review Details
08/08/2025 RESIDENTIAL SOLAR v.2 08/08/2025 REQUIRES RESUBMIT Review Details

Completed Inspections

Permit Status: Inspections
Permit Number: TC-RES-0625-02995
Permit Description: REV_1, Equipment Relocation + Trenching; House 2- Installation of a 6.56kw PV System with Battery and 225A MPU
Total Completed Inspections - 4
Date Description Inspector Results Comments
04/15/2026 COT - RSOL - Electrical Underground Solar Project Passed
04/15/2026 BULD - Electrical Clearance Passed Clearance for TEP DGC/BAT. Unit #2 4/15/2025
04/15/2026 RSBU - Building Final Passed
04/15/2026 COT - RSOL - Electrical Final Solar Project Passed