Permit: TC-RES-0625-02881
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
442 S STRATFORD DR
Address NEW:
442 S STRATFORD DR
Apply Date:
06/04/2025
Applicant:
TFS Solar
Description:
Roof mount 7.83 kW DC photovoltaic solar system; 18 modules. 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 4 strings. 100A bus with 100A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
Permit Reviews
Permit Number - TC-RES-0625-02881
Permit Status: Complete
Permit Description: Roof mount 7.83 kW DC photovoltaic solar system; 18 modules. 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 4 strings. 100A bus with 100A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/04/2025 | RESIDENTIAL SOLAR v.1 | 07/01/2025 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-RES-0625-02881
Permite Description: Roof mount 7.83 kW DC photovoltaic solar system; 18 modules. 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 4 strings. 100A bus with 100A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/29/2025 | BULD - Electrical Clearance | N/A | Partial Pass | Partial pass for Tesla meter switch, pending solar, CLEARANCE DGL. Called Marcia 7/29/25 9:55 to restore power |
| 08/04/2025 | COT - RSOL - Electrical Progress Solar Project | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0625-02881
Permit Description: Roof mount 7.83 kW DC photovoltaic solar system; 18 modules. 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 4 strings. 100A bus with 100A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/04/2025 | BULD - Electrical Clearance | Passed | Approved solar with PW 3 - DGC/BAT Clearance is required for the solar meter | |
| 08/04/2025 | COT - RSOL - Electrical Final Solar Project | Passed |