Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Apply Date:
06/11/2024
Applicant:
Gregory Moore
Description:
Individual unit permit

Permit Reviews

Permit Number - TC-RES-0624-03528
Permit Status: Complete
Permit Description: Individual unit permit
Start Date Submittal Complete Date Status  
09/18/2024 RESIDENTIAL NEW DWELLING v.2 10/18/2024 APPROVED Review Details
02/14/2025 RESIDENTIAL ADU REVISION v.2 02/24/2025 REQUIRES RESUBMIT Review Details
01/09/2025 RESIDENTIAL ADU REVISION v.1 01/30/2025 REQUIRES RESUBMIT Review Details
02/24/2025 RESIDENTIAL ADU REVISION v.3 02/27/2025 APPROVED Review Details
06/17/2024 RESIDENTIAL NEW DWELLING v.1 07/23/2024 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-RES-0624-03528
Permit Status: Complete
Permit Description: Individual unit permit
Date Description Comments
06/17/2024 Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512
11/18/2025 Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections.
10/18/2024 The Contractor you have added to your permit cannot be verified. Please contact staff to have the ROC number added to the account.
10/01/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
10/01/2024 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
10/25/2024 Full payment of Impact fees required prior to issue of CofO/LOC
02/27/2025 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.
10/01/2024 Post-Installed Anchor Inspection Report is required.
02/27/2025 Post-Tension Inspection Report is required.
10/01/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
10/01/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-RES-0624-03528
Permite Description: Individual unit permit
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
12/02/2025 RSBU - Building Final N/A Partial Pass Partial pass. Pending other inspections. 12/2/2025

Completed Inspections

Permit Status: Complete
Permit Number: TC-RES-0624-03528
Permit Description: Individual unit permit
Total Completed Inspections - 20
Date Description Inspector Results Comments
05/06/2025 COT - RSPL - Rough Soil Passed 5-6-25, sewer connection together with underground plumbing verified per plans and under test. Okay to backfill-shading required.
05/06/2025 COT - RSPL - Sewer Passed 5-6-25, sewer connection together with underground plumbing verified per plans and under test. Okay to backfill-shading required.
05/19/2025 COT - RSBU - Excavation/Rebar/Zoning Passed 5-19-25, rebar/setbacks/excavation approved. Okay to pour concrete.
05/19/2025 COT - RSBU - Preslab Passed 5-19-25, preslab verified per plans. Okay to pour concrete.
05/19/2025 COT - RSEL - Electrical Underground Passed 5-19-25, underground electrical conduits verified per plans. Okay to pour concrete.
07/08/2025 COT - RSPL - Yard Water Line Passed Approved 3/4" copper water supply from existing main line PVC stub out to Unit #1112 (Bldg1), okay to shade fill progress areas
07/09/2025 COT - RSBU - Roof Nailing Passed
09/08/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
09/08/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
09/08/2025 COT - RSEL - Grounding/Bonding Passed
09/08/2025 BULD - Electrical Clearance Passed 9/8/25:Ok to set meters . Code: ECO UNIT 1112
09/11/2025 COT - RSBU - Firewall/Fire Barrier/Firestop Passed 9-11-25:approved. Okay to dry-wall.
09/17/2025 COT - RSBU - Interior Shear Bracing Passed 9-17-25: okay for tape & texture.
12/02/2025 COT - RSBU - Stem Wall/Retaining Wall Passed
12/02/2025 COT - RSEL - Electrical Final Passed
12/02/2025 COT - RSEL - Outdoor Lighting Passed
12/02/2025 COT - RSME - Mechanical Final Passed
12/02/2025 COT - RSPL - Backwater Valve Passed
12/02/2025 COT - RSPL - Plumbing Final Passed
12/18/2025 RSBU - Building Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL (SSRS).PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
23-112 RIO AZUL APARTMENTS RIO AZUL PARTNERS LLC_V1.PDF DOCUMENTS VIEW
CONS-RIO AZUL FINAL_V2.PDF DOCUMENTS VIEW
SPECIAL INSPECTION CERTIFICATE 1112-2024-09-12_V1.PDF DOCUMENTS VIEW