Permit: TC-RES-0623-05827
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
757 W SANTA MARIA ST
Address NEW:
757 W SANTA MARIA ST
Apply Date:
06/11/2023
Applicant:
Francisco SOTO
Description:
Bedroom and Bathroom Addition
Permit Reviews
Permit Number - TC-RES-0623-05827
Permit Status: Issued
Permit Description: Bedroom and Bathroom Addition
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/12/2023 | RESIDENTIAL NEW DWELLING v.1 | 07/05/2023 | APPROVED |
Conditions
Permit Number - TC-RES-0623-05827
Permit Status: Issued
Permit Description: Bedroom and Bathroom Addition
| Date | Description | Comments |
|---|---|---|
| 07/05/2023 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/integrated-planning/PDSD/PDSD_Owner_Builder_Affidavit.pdf, is required prior to issuance of permit. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-RES-0623-05827
Permite Description: Bedroom and Bathroom Addition
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/19/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Partial Pass | 9/19/23: electrical and plumbing passed, mini split will need to be added to plans (revision required for mechanical) |
Completed Inspections
Permit Status: Issued
Permit Number: TC-RES-0623-05827
Permit Description: Bedroom and Bathroom Addition
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/09/2023 | COT - RSBU - Preslab | Passed | Footing is dug 12" into native soil. Rebar reinforcement is properly in place, ufer ground is attached to rebar reinforcement. Forms are set for concrete slab on grade. Okay to pour concrete. | |
| 08/09/2023 | COT - RSPL - Rough Soil | Passed | Underground plumbing is holding a water test. Okay to shade pipes and backfill trenches. | |
| 08/09/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Footing is dug 12" into native soil. Rebar reinforcement is properly in place, ufer ground is attached to rebar reinforcement. | |
| 08/09/2023 | COT - RSEL - Grounding/Bonding | Passed | Footing is dug 12" into native soil. Rebar reinforcement is properly in place, ufer ground is attached to rebar reinforcement. | |
| 08/30/2023 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 8/30/23: window in bedroom will need to meet proper egress height no more than 44". will be checked at intermediate | |
| 08/30/2023 | COT - RSBU - Roof Nailing | Passed | 8/30/23: Roof nailing passed electrical panel must be relocated to exterior of addition before installation of missing roof sheathing. | |
| 09/19/2023 | BULD - Electrical Clearance | Passed | 9/19/23: TEP INCR (panel relocated) cutover scheduling | |
| 12/07/2023 | COT - RSPL - Plumbing Final | Passed | ||
| 12/07/2023 | COT - RSEL - Electrical Final | Passed | 12/7/23: condenser unit not securely fastened to roof. Toilet not caulked, Vents above roof line need to be painted. 12/7/23: all corrections made |
|
| 12/07/2023 | COT - RSME - Mechanical Final | Passed | 12/7/23: condenser unit not securely fastened to roof. Toilet not caulked, Vents above roof line need to be painted. 12/7/23: all corrections made |
|
| 12/07/2023 | RSBU - Building Final | Passed | 12/7/23: condenser unit not securely fastened to roof. Toilet not caulked, Vents above roof line need to be painted. 12/7/23: all corrections made |