Permit: TC-RES-0623-05590
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
4132 E POE ST
Address NEW:
4132 E POE ST
Apply Date:
06/01/2023
Applicant:
Enrique Durazo
Description:
Bedroom and Bathroom Addition
Permit Reviews
Permit Number - TC-RES-0623-05590
Permit Status: Complete
Permit Description: Bedroom and Bathroom Addition
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/02/2023 | RESIDENTIAL NEW DWELLING v.1 | 06/27/2023 | REQUIRES RESUBMIT |
| 07/25/2023 | RESTAMP - RESIDENTIAL v.1 | 07/25/2023 | APPROVED |
| 07/18/2023 | RESIDENTIAL NEW DWELLING v.2 | 07/25/2023 | APPROVED |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0623-05590
Permit Description: Bedroom and Bathroom Addition
Total Completed Inspections - 12
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/09/2023 | COT - RSPL - Rough Soil | Passed | Approved to 2-way clean out outside of addition, okay to continue pre-slab | |
| 08/15/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 08/15/2023 | COT - RSBU - Preslab | Passed | ||
| 09/01/2023 | COT - RSPL - Sewer | Passed | ||
| 09/12/2023 | COT - RSBU - Roof Nailing | Passed | ||
| 09/14/2023 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 10/13/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 9/1/23: not ready contractor called this inspection to get the correct one 10/13/23: passed |
|
| 11/22/2023 | RSBU - Building Final | Passed | Room addition is complete. Mechanical, electrical, plumbing are complete and fully functional. Okay to issue Certificate of Completion for permit. | |
| 11/22/2023 | COT - RSEL - Electrical Final | Passed | Room addition is complete. Mechanical, electrical, plumbing are complete and fully functional. Okay to issue Certificate of Completion for permit. | |
| 11/22/2023 | COT - RSME - Mechanical Final | Passed | Room addition is complete. Mechanical, electrical, plumbing are complete and fully functional. Okay to issue Certificate of Completion for permit. | |
| 11/22/2023 | COT - RSPL - Gas Pressure Test | Passed | new insta-hot water heater for addition is connected to existing gas service and fully operational. | |
| 11/22/2023 | COT - RSPL - Plumbing Final | Passed | Room addition is complete. Mechanical, electrical, plumbing are complete and fully functional. Okay to issue Certificate of Completion for permit. |