Permit: TC-RES-0526-02656
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
1025 E ALTA VISTA ST
Address NEW:
1025 E ALTA VISTA ST
Apply Date:
05/19/2026
Applicant:
TFS Solar
Description:
13.5 kWh Storage, 1 Tesla Powerwall-3 battery on 60A interconnection breaker. Use existing trench from battery to service panel. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
Permit Reviews
Permit Number - TC-RES-0526-02656
Permit Status: Complete
Permit Description: 13.5 kWh Storage, 1 Tesla Powerwall-3 battery on 60A interconnection breaker. Use existing trench from battery to service panel. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/19/2026 | RESIDENTIAL SIMPLE REVIEW v.1 | 05/20/2026 | APPROVED |
Conditions
Permit Number - TC-RES-0526-02656
Permit Status: Complete
Permit Description: 13.5 kWh Storage, 1 Tesla Powerwall-3 battery on 60A interconnection breaker. Use existing trench from battery to service panel. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
| Date | Description | Comments |
|---|---|---|
| 05/19/2026 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0526-02656
Permit Description: 13.5 kWh Storage, 1 Tesla Powerwall-3 battery on 60A interconnection breaker. Use existing trench from battery to service panel. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/02/2026 | BULD - Electrical Clearance | Passed | ||
| 07/02/2026 | COT - RSEL - Electrical Final | Passed | ||
| 07/02/2026 | COT - RSEL - Electrical Underground | Passed |