Permit: TC-RES-0525-02661
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
3535 E MONTHAN SV
Address NEW:
3535 E MONTHAN SV
Apply Date:
05/21/2025
Applicant:
Dean Bagley
Description:
- We will begin by digging down at the meter and digging underneath the block wall. - We will then trench under the block wall. - Once under the block wall, we will go onto the other side and move bricks from the area. - We will then trench down 18” along 20ft. - We will then go home and move the stove and cut drywall, and drill a hole up onto the roof. - We will then go into the water heater closet and drill a hole up onto the roof. - Once the area is fully prepped for the new line, we will run a tee off the meter, tying into the furnace for the pool, and running a line into the trench up to the house, going up and over along roof. - We then tee off line and run a section of pipe going to the stove and a section going to the water heater, installing new sediment traps as needed, as well as new gas valves and supply lines. - Once finished, we will put the system to test and submit permits. - Once permits are completed, we will then backfill and clean up any debris.
Permit Reviews
Permit Number - TC-RES-0525-02661
Permit Status: Complete
Permit Description: - We will begin by digging down at the meter and digging underneath the block wall.
- We will then trench under the block wall.
- Once under the block wall, we will go onto the other side and move bricks from the area.
- We will then trench down 18” along 20ft.
- We will then go home and move the stove and cut drywall, and drill a hole up onto the roof.
- We will then go into the water heater closet and drill a hole up onto the roof.
- Once the area is fully prepped for the new line, we will run a tee off the meter, tying into the furnace for the pool, and running a line into the trench up to the house, going up and over along roof.
- We then tee off line and run a section of pipe going to the stove and a section going to the water heater, installing new sediment traps as needed, as well as new gas valves and supply lines.
- Once finished, we will put the system to test and submit permits.
- Once permits are completed, we will then backfill and clean up any debris.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/21/2025 | RESIDENTIAL SIMPLE REVIEW v.1 | 05/21/2025 | REQUIRES RESUBMIT |
| 05/23/2025 | RESIDENTIAL SIMPLE REVIEW v.2 | 05/26/2025 | APPROVED |
Conditions
Permit Number - TC-RES-0525-02661
Permit Status: Complete
Permit Description: - We will begin by digging down at the meter and digging underneath the block wall.
- We will then trench under the block wall.
- Once under the block wall, we will go onto the other side and move bricks from the area.
- We will then trench down 18” along 20ft.
- We will then go home and move the stove and cut drywall, and drill a hole up onto the roof.
- We will then go into the water heater closet and drill a hole up onto the roof.
- Once the area is fully prepped for the new line, we will run a tee off the meter, tying into the furnace for the pool, and running a line into the trench up to the house, going up and over along roof.
- We then tee off line and run a section of pipe going to the stove and a section going to the water heater, installing new sediment traps as needed, as well as new gas valves and supply lines.
- Once finished, we will put the system to test and submit permits.
- Once permits are completed, we will then backfill and clean up any debris.
| Date | Description | Comments |
|---|---|---|
| 05/26/2025 | The Contractor you have added to your permit cannot be verified. Please contact staff to have the ROC number added to the account. | |
| 05/21/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0525-02661
Permit Description: - We will begin by digging down at the meter and digging underneath the block wall.
- We will then trench under the block wall.
- Once under the block wall, we will go onto the other side and move bricks from the area.
- We will then trench down 18” along 20ft.
- We will then go home and move the stove and cut drywall, and drill a hole up onto the roof.
- We will then go into the water heater closet and drill a hole up onto the roof.
- Once the area is fully prepped for the new line, we will run a tee off the meter, tying into the furnace for the pool, and running a line into the trench up to the house, going up and over along roof.
- We then tee off line and run a section of pipe going to the stove and a section going to the water heater, installing new sediment traps as needed, as well as new gas valves and supply lines.
- Once finished, we will put the system to test and submit permits.
- Once permits are completed, we will then backfill and clean up any debris.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/30/2025 | COT - BULD - SWG Clearance | Passed | 5.30.25 lines verified at appropriate depth, gauge functional and under test at 15psi. Shut off valves verified. Properly sealed at roof and supported. Approved. | |
| 05/30/2025 | RSBU - Building Final | Passed | 5.30.25 lines verified at appropriate depth, gauge functional and under test at 15psi. Shut off valves verified. Properly sealed at roof and supported. Approved. | |
| 05/30/2025 | COT - RSPL - Plumbing Final | Passed | 5.30.25 lines verified at appropriate depth, gauge functional and under test at 15psi. Shut off valves verified. Properly sealed at roof and supported. Approved. | |
| 05/30/2025 | RSPL - Plumbing Progress | Passed | 5.30.25 lines verified at appropriate depth, gauge functional and under test at 15psi. Shut off valves verified. Properly sealed at roof and supported. Approved. |