Permit: TC-RES-0523-05401
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
726 S 7TH AV
Address NEW:
726 S 7TH AV
Apply Date:
05/23/2023
Applicant:
Amanda Gattenby
Description:
Sleeping Quarters
Permit Reviews
Permit Number - TC-RES-0523-05401
Permit Status: Complete
Permit Description: Sleeping Quarters
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/25/2023 | RESIDENTIAL NEW DWELLING v.1 | 06/22/2023 | REQUIRES RESUBMIT |
| 10/24/2023 | RESTAMP - RESIDENTIAL v.1 | 10/30/2023 | APPROVED |
| 08/21/2023 | RESIDENTIAL NEW DWELLING v.2 | 09/05/2023 | REQUIRES RESUBMIT |
| 10/11/2023 | RESIDENTIAL NEW DWELLING v.3 | 10/24/2023 | APPROVED |
Conditions
Permit Number - TC-RES-0523-05401
Permit Status: Complete
Permit Description: Sleeping Quarters
| Date | Description | Comments |
|---|---|---|
| 10/30/2023 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as a contact. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0523-05401
Permit Description: Sleeping Quarters
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/13/2023 | COT - RSPL - Sewer | Passed | Okay to backfill. Shading required. 12/13/2023 | |
| 12/13/2023 | COT - RSPL - Yard Water Line | Passed | Okay to backfill. Shading required. 12/13/2023 | |
| 12/13/2023 | COT - RSPL - Rough Soil | Passed | Okay to backfill. Shading required. 12/13/2023 | |
| 12/20/2023 | COT - RSBU - Preslab | Passed | 12/20/23: reinforcement per plans for Preslab ok to pour. | |
| 01/08/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 01/08/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 01/11/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Ok to insulate and sheet rock throughout. | |
| 01/24/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | Corrections were made per engineer request. 1/24/2024 | |
| 02/15/2024 | COT - RSEL - Electrical Underground | Passed | OK to cover progress areas. | |
| 02/22/2024 | RSBU - Building Final | Passed | ||
| 02/22/2024 | COT - RSEL - Electrical Final | Passed | ||
| 02/22/2024 | COT - RSME - Mechanical Final | Passed | ||
| 02/22/2024 | COT - RSPL - Plumbing Final | Passed |