Permit: TC-RES-0326-01422
Permit Details
Status:
Inspections
Type:
Residential Building - One or Two Family
Address:
4740 E TOWNER ST UNIT 2
Address NEW:
4740 E TOWNER ST UNIT 2
Apply Date:
03/22/2026
Applicant:
Antonio Romano
Description:
ADU: Addition to Bathroom started with permit TC RES-1025-05277
Permit Reviews
Permit Number - TC-RES-0326-01422
Permit Status: Inspections
Permit Description: ADU: Addition to Bathroom started with permit TC RES-1025-05277
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/25/2026 | RESIDENTIAL ADU v.1 | 04/08/2026 | REQUIRES RESUBMIT |
| 05/15/2026 | RESIDENTIAL ADU v.3 | 05/20/2026 | APPROVED |
| 05/07/2026 | RESIDENTIAL ADU v.2 | 05/13/2026 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-RES-0326-01422
Permit Status: Inspections
Permit Description: ADU: Addition to Bathroom started with permit TC RES-1025-05277
| Date | Description | Comments |
|---|---|---|
| 03/25/2026 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-RES-0326-01422
Permite Description: ADU: Addition to Bathroom started with permit TC RES-1025-05277
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/02/2026 | COT - RSEL - Grounding/Bonding | N/A | Not Ready | Not ready, currently at Intermediate. |
| 07/02/2026 | COT - RSEL - Outdoor Lighting | N/A | Not Ready | |
| 07/02/2026 | COT - RSPL - Plumbing Final | N/A | Not Ready | Not ready, currently at Intermediate. |
| 07/02/2026 | COT - RSEL - Electrical Final | N/A | Not Ready | Not ready, currently at Intermediate. |
| 07/22/2026 | COT - RSME - Mechanical Final | N/A | Partial Pass | Partial pass kitchen hood vent |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-RES-0326-01422
Permit Description: ADU: Addition to Bathroom started with permit TC RES-1025-05277
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/22/2026 | RSPL - Plumbing Progress | Passed | ||
| 06/02/2026 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Passed | |
| 06/23/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 06/24/2026 | COT - RSBU - Preslab | Passed | ||
| 06/24/2026 | COT - RSEL - Electrical Underground | Passed | ||
| 06/24/2026 | COT - RSPL - Rough Soil | Passed | ||
| 06/24/2026 | RSEL - Electrical Progress | Passed | ||
| 06/24/2026 | COT - RSBU - Roof Nailing | Passed | ||
| 07/02/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 07/02/2026 | COT - RSPL - Sewer | Passed | ||
| 07/16/2026 | RSME - Mechanical Progress | Passed | verified exhaust fans . 7/16/2026 | |
| 07/27/2026 | COT - RSBU - Firewall/Fire Barrier/Firestop | Passed | ||
| 07/27/2026 | COT - RSBU - Interior Shear Bracing | Passed |