Permit: TC-RES-0325-01650
Permit Details
Status:
Inspections Complete
Type:
Residential Building - One or Two Family
Address:
124 N OLSEN AV UNIT 3
Address NEW:
124 N OLSEN AV UNIT 3
Apply Date:
03/30/2025
Applicant:
alex enoch
Description:
ADU
Permit Reviews
Permit Number - TC-RES-0325-01650
Permit Status: Inspections complete
Permit Description: ADU
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/16/2025 | RESIDENTIAL NEW DWELLING v.1 | 05/14/2025 | REQUIRES RESUBMIT |
| 05/19/2025 | RESIDENTIAL NEW DWELLING v.2 | 05/26/2025 | APPROVED |
| 11/10/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/10/2025 | APPROVED |
| 05/26/2025 | RESTAMP - RESIDENTIAL v.1 | 05/27/2025 | APPROVED |
Conditions
Permit Number - TC-RES-0325-01650
Permit Status: Inspections complete
Permit Description: ADU
| Date | Description | Comments |
|---|---|---|
| 05/12/2025 | Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512 | |
| 04/16/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 05/12/2025 |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-0325-01650
Permite Description: ADU
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/09/2025 | COT - RSPL - Rough Soil | N/A | Re-inspection required | 6/9/25: Tracer wire required on all plumbing lines outside of building slab, sewer must be 12'' below grade to the top of the pipe, plumbing underground not per plan vents missing throughout. |
| 07/02/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Partial Pass | 7/2/25 1. Partial pass; Water Closet too close to Tub, must be a minimum of 15" away from flange center. 2. Entrance threshold is too high, must be no higher than 1/2" from grade. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-0325-01650
Permit Description: ADU
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/09/2025 | COT - RSPL - Yard Water Line | Passed | ||
| 06/11/2025 | COT - RSPL - Rough Soil | Passed | Ok to cover progress areas. | |
| 06/17/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Rebar and footings per plan, tie downs and electric underground present, ok to pour concrete | |
| 06/17/2025 | COT - RSBU - Preslab | Passed | Rebar and footings per plan, tie downs and electric underground present, ok to pour concrete | |
| 06/17/2025 | COT - RSEL - Electrical Underground | Passed | Rebar and footings per plan, tie downs and electric underground present, ok to pour concrete | |
| 06/24/2025 | COT - RSBU - Roof Nailing | Passed | ||
| 06/25/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 07/02/2025 | COT - RSEL - Grounding/Bonding | Passed | ||
| 07/14/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 7/14/25 Pass, threshold will be checked at Final; currently have a 9" high landing at entrance. |
|
| 08/04/2025 | BULD - Electrical Clearance | Passed | ECO CLEARANCE FOR NEW ADU | |
| 08/20/2025 | RSBU - Building Final | Passed | ||
| 08/20/2025 | COT - RSEL - Electrical Final | Passed | ||
| 08/20/2025 | COT - RSEL - Outdoor Lighting | Passed | ||
| 08/20/2025 | COT - RSME - Mechanical Final | Passed | ||
| 08/20/2025 | COT - RSPL - Plumbing Final | Passed |