Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-RES-0325-01590
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
1901 N AVENIDA AZAHAR
Address NEW:
1901 N AVENIDA AZAHAR
Apply Date:
03/26/2025
Applicant:
Hailey McGaw
Description:
(42)HYPERION SOLAR HY-DH108P8B-405 (405W) (42)ENPHASE IQ8MC-72-M-US (240V) APROX. 60' DC TRENCHED CONDUIT RUN PHOTOVOLTAIC ARRAY ON THE STEEL CANOPY (N) SOLAR METER SOCKET ADAPTER (MSA)
Permit Reviews
Permit Number - TC-RES-0325-01590
Permit Status: Issued
Permit Description: (42)HYPERION SOLAR HY-DH108P8B-405 (405W)
(42)ENPHASE IQ8MC-72-M-US (240V)
APROX. 60' DC TRENCHED CONDUIT RUN
PHOTOVOLTAIC ARRAY ON THE STEEL CANOPY
(N) SOLAR METER SOCKET ADAPTER (MSA)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/21/2025 | RESTAMP - RESIDENTIAL v.1 | 07/24/2025 | APPROVED |
| 03/27/2025 | RESIDENTIAL SOLAR v.1 | 05/19/2025 | REQUIRES RESUBMIT |
| 09/05/2025 | RESIDENTIAL SOLAR REVISION v.1 | 09/26/2025 | APPROVED |
| 05/27/2025 | RESIDENTIAL SOLAR v.2 | 06/24/2025 | REQUIRES RESUBMIT |
| 06/25/2025 | RESIDENTIAL SOLAR v.3 | 07/21/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-RES-0325-01590
Permit Status: Issued
Permit Description: (42)HYPERION SOLAR HY-DH108P8B-405 (405W)
(42)ENPHASE IQ8MC-72-M-US (240V)
APROX. 60' DC TRENCHED CONDUIT RUN
PHOTOVOLTAIC ARRAY ON THE STEEL CANOPY
(N) SOLAR METER SOCKET ADAPTER (MSA)
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 07/18/2025 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 07/18/2025 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
| 07/18/2025 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. |
| 07/18/2025 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-RES-0325-01590
Permite Description: (42)HYPERION SOLAR HY-DH108P8B-405 (405W)
(42)ENPHASE IQ8MC-72-M-US (240V)
APROX. 60' DC TRENCHED CONDUIT RUN
PHOTOVOLTAIC ARRAY ON THE STEEL CANOPY
(N) SOLAR METER SOCKET ADAPTER (MSA)
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/26/2025 | RSBU - Building Final | N/A | Canceled | by contractor |
Completed Inspections
Permit Status: Issued
Permit Number: TC-RES-0325-01590
Permit Description: (42)HYPERION SOLAR HY-DH108P8B-405 (405W)
(42)ENPHASE IQ8MC-72-M-US (240V)
APROX. 60' DC TRENCHED CONDUIT RUN
PHOTOVOLTAIC ARRAY ON THE STEEL CANOPY
(N) SOLAR METER SOCKET ADAPTER (MSA)
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/14/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 08/14/2025 | COT - RSOL - Grounding/Bonding Solar Project | Passed | 8.14.25 Grounding wire verified Passed |
|
| 08/21/2025 | COT - RSOL - Electrical Underground Solar Project | Passed | Approved underground electrical conduits from service equipment to solar structure, okay to backfill progress areas | |
| 08/29/2025 | BULD - Electrical Clearance | Passed | 8.29.25 PARTIAL PASS PENDING REVISION FOR DISCONNECT Equipment has been inspected, only remaining task for inspection is to verify that the revision has been submitted and accepted. FOR FUTURE INSPECTOR: Reach out to Anthony Caballero with any questions. |
|
| 09/30/2025 | RSBU - Building Final | Passed | 9.30.2025 Corrections made to prior inspection on 8.29.2025. Disconnect per plan is 100A fused with 4AWG wires. |
|
| 09/30/2025 | COT - RSOL - Electrical Final Solar Project | Passed | 9.30.2025 Corrections made to prior inspection on 8.29.2025. Disconnect per plan is 100A fused with 4AWG wires. |