Permit: TC-RES-0226-00950
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
3050 N DASYLIRION DR
Address NEW:
3050 N DASYLIRION DR
Apply Date:
02/24/2026
Applicant:
TFS Solar
Description:
1 Tesla Powerwall-3 battery only added to existing PV system. 60A interconnection for battery circuit. Existing 30A PV breaker on 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
Permit Reviews
Permit Number - TC-RES-0226-00950
Permit Status: Complete
Permit Description: 1 Tesla Powerwall-3 battery only added to existing PV system. 60A interconnection for battery circuit. Existing 30A PV breaker on 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/24/2026 | RESIDENTIAL SOLAR v.1 | 03/23/2026 | APPROVED |
Conditions
Permit Number - TC-RES-0226-00950
Permit Status: Complete
Permit Description: 1 Tesla Powerwall-3 battery only added to existing PV system. 60A interconnection for battery circuit. Existing 30A PV breaker on 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
| Date | Description | Comments |
|---|---|---|
| 02/24/2026 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0226-00950
Permit Description: 1 Tesla Powerwall-3 battery only added to existing PV system. 60A interconnection for battery circuit. Existing 30A PV breaker on 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/08/2026 | BULD - Electrical Clearance | Passed | Verbal clearance to TEP DGL. (Tesla backup switch) BAT Clearance included same day inspection. No new solar added. 4/8/2026 |
|
| 04/08/2026 | COT - RSOL - Electrical Final Solar Project | Passed |