Permit: TC-RES-0226-00926
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
2224 S KELVIN SV
Address NEW:
2224 S KELVIN SV
Apply Date:
02/23/2026
Applicant:
TFS Solar
Description:
Roof mount 10.01 kW DC photovoltaic solar system; 23 modules; 27 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 4 strings. 1 battery expansion pack, (no inverter); 125A bus with 100A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
Permit Reviews
Permit Number - TC-RES-0226-00926
Permit Status: Complete
Permit Description: Roof mount 10.01 kW DC photovoltaic solar system; 23 modules; 27 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 4 strings. 1 battery expansion pack, (no inverter); 125A bus with 100A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/24/2026 | RESIDENTIAL SOLAR v.1 | 03/18/2026 | APPROVED |
Conditions
Permit Number - TC-RES-0226-00926
Permit Status: Complete
Permit Description: Roof mount 10.01 kW DC photovoltaic solar system; 23 modules; 27 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 4 strings. 1 battery expansion pack, (no inverter); 125A bus with 100A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
| Date | Description | Comments |
|---|---|---|
| 02/24/2026 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0226-00926
Permit Description: Roof mount 10.01 kW DC photovoltaic solar system; 23 modules; 27 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 4 strings. 1 battery expansion pack, (no inverter); 125A bus with 100A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/21/2026 | BULD - Electrical Clearance | Passed | 4.21.26 Approved for DGC/bat |