Permit: TC-RES-0226-00817
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
9037 S CEDARBROOK LN
Address NEW:
9037 S CEDARBROOK LN
Apply Date:
02/17/2026
Applicant:
TFS Solar
Description:
Roof mount 6.53 kW DC photovoltaic solar system; 15 modules; 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
Permit Reviews
Permit Number - TC-RES-0226-00817
Permit Status: Complete
Permit Description: Roof mount 6.53 kW DC photovoltaic solar system; 15 modules; 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/02/2026 | RESIDENTIAL SOLAR v.2 | 03/02/2026 | APPROVED |
| 02/19/2026 | RESIDENTIAL SOLAR v.1 | 02/25/2026 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-RES-0226-00817
Permit Status: Complete
Permit Description: Roof mount 6.53 kW DC photovoltaic solar system; 15 modules; 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
| Date | Description | Comments |
|---|---|---|
| 02/19/2026 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0226-00817
Permit Description: Roof mount 6.53 kW DC photovoltaic solar system; 15 modules; 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/21/2026 | BULD - Electrical Clearance | Passed | 04/21/2026 Approved clearance TEP DGC/BAT. |
|
| 04/21/2026 | COT - RSOL - Electrical Final Solar Project | Passed | ||