Permit: TC-RES-0226-00541
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
1334 S MAGNOLIA AV
Address NEW:
1334 S MAGNOLIA AV
Apply Date:
02/03/2026
Applicant:
TFS Solar
Description:
Roof mount 5.22 kW DC photovoltaic solar system; 12 modules; 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 1 string. 100A meter base with 125A bus with 100A MCB. Interconnection via PCS, Tesla Backup Switch for whole home backup.
Permit Reviews
Permit Number - TC-RES-0226-00541
Permit Status: Complete
Permit Description: Roof mount 5.22 kW DC photovoltaic solar system; 12 modules; 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 1 string. 100A meter base with 125A bus with 100A MCB. Interconnection via PCS, Tesla Backup Switch for whole home backup.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/04/2026 | RESIDENTIAL SOLAR v.1 | 02/13/2026 | REQUIRES RESUBMIT |
| 02/19/2026 | RESIDENTIAL SOLAR v.2 | 02/19/2026 | APPROVED |
Conditions
Permit Number - TC-RES-0226-00541
Permit Status: Complete
Permit Description: Roof mount 5.22 kW DC photovoltaic solar system; 12 modules; 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 1 string. 100A meter base with 125A bus with 100A MCB. Interconnection via PCS, Tesla Backup Switch for whole home backup.
| Date | Description | Comments |
|---|---|---|
| 02/04/2026 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0226-00541
Permit Description: Roof mount 5.22 kW DC photovoltaic solar system; 12 modules; 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 1 string. 100A meter base with 125A bus with 100A MCB. Interconnection via PCS, Tesla Backup Switch for whole home backup.
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/15/2026 | BULD - Electrical Clearance | Passed | Clearance for TEP DGC/BAT. 4/15/2026 | |
| 04/15/2026 | RSBU - Building Final | Passed | ||
| 04/15/2026 | COT - RSOL - Electrical Final Solar Project | Passed |