Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Apply Date:
02/14/2025
Applicant:
Richard Spreiser
Description:
ADU

Permit Reviews

Permit Number - TC-RES-0225-00850
Permit Status: Complete
Permit Description: ADU
Start Date Submittal Complete Date Status  
02/14/2025 RESIDENTIAL NEW DWELLING v.1 03/19/2025 REQUIRES RESUBMIT Review Details
04/09/2025 RESIDENTIAL NEW DWELLING v.2 05/07/2025 APPROVED Review Details

Conditions

Permit Number - TC-RES-0225-00850
Permit Status: Complete
Permit Description: ADU
Date Description Comments
02/14/2025 Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512
02/14/2025 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-RES-0225-00850
Permite Description: ADU
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
09/24/2025 BULD - Electrical Clearance N/A Not Applicable
09/24/2025 COT - BULD - SWG Clearance N/A Not Applicable

Completed Inspections

Permit Status: Complete
Permit Number: TC-RES-0225-00850
Permit Description: ADU
Total Completed Inspections - 14
Date Description Inspector Results Comments
05/12/2025 COT - RSPL - Rough Soil Passed
05/14/2025 COT - RSBU - Preslab Passed Ensure slab area is termite treated
05/14/2025 COT - RSBU - Excavation/Rebar/Zoning Passed Footings for guest house and pool bathroom. Ok to place concrete in progress areas.
06/06/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed Ok to cover exterior walls
06/06/2025 COT - RSBU - Roof Nailing Passed Ok to dry-in roof system.
06/06/2025 COT - RSEL - Electrical Underground Passed
06/06/2025 COT - RSPL - Yard Water Line Passed
06/18/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
06/18/2025 COT - RSEL - Grounding/Bonding Passed
09/24/2025 COT - RSME - Mechanical Final Passed
09/24/2025 COT - RSPL - Plumbing Final Passed
09/25/2025 RSBU - Building Final Passed
09/25/2025 COT - RSPL - Gas Pressure Test Passed
09/25/2025 COT - RSEL - Electrical Final Passed Approved. Corrections were made. 9/25/2025

Documents

File Name Document Type  
COFO_FINALCOFO_RESIDENTIAL.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-2_2315 E WAVERLY ST ADU CD SET_V2.PDF DOCUMENTS VIEW