Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Address NEW:
780 W LIGHTSTAR CI
Apply Date:
02/27/2024
Applicant:
Marytine Ramos
Description:
Installation of Roof Mounted 10.80kW PV System / Supply Breaker / Sub-panel

Permit Reviews

Permit Number - TC-RES-0224-01131
Permit Status: Complete
Permit Description: Installation of Roof Mounted 10.80kW PV System / Supply Breaker / Sub-panel
Start Date Submittal Complete Date Status  
04/26/2024 RESIDENTIAL SOLAR v.3 04/29/2024 APPROVED Review Details
03/22/2024 RESIDENTIAL SOLAR v.2 03/28/2024 APPROVED Review Details
04/26/2024 RESIDENTIAL SOLAR v.2 04/26/2024 REQUIRES RESUBMIT Review Details
04/25/2024 RESIDENTIAL SOLAR v.1 04/25/2024 REQUIRES RESUBMIT Review Details
02/27/2024 RESIDENTIAL SOLAR v.1 03/19/2024 REQUIRES RESUBMIT Review Details

Completed Inspections

Permit Status: Complete
Permit Number: TC-RES-0224-01131
Permit Description: Installation of Roof Mounted 10.80kW PV System / Supply Breaker / Sub-panel
Total Completed Inspections - 5
Date Description Inspector Results Comments
05/07/2024 BULD - Electrical Clearance Passed Approved, DGC Clearance to TEP is required for the solar meter
05/07/2024 COT - RSOL - Electrical Underground Solar Project Passed
05/07/2024 COT - RSOL - Grounding/Bonding Solar Project Passed
05/07/2024 RSBU - Building Final Passed
05/07/2024 COT - RSOL - Electrical Final Solar Project Passed