Permit: TC-RES-0223-02974
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
2503 E 4TH ST
Address NEW:
2503 E 4TH ST
Apply Date:
02/20/2023
Applicant:
Robert Gardner
Description:
Bedroom Bathroom Addition
Permit Reviews
Permit Number - TC-RES-0223-02974
Permit Status: Complete
Permit Description: Bedroom Bathroom Addition
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/28/2023 | RESIDENTIAL NEW DWELLING v.1 | 03/27/2023 | REQUIRES RESUBMIT |
| 04/27/2023 | RESIDENTIAL NEW DWELLING v.2 | 05/19/2023 | APPROVED |
Conditions
Permit Number - TC-RES-0223-02974
Permit Status: Complete
Permit Description: Bedroom Bathroom Addition
| Date | Description | Comments |
|---|---|---|
| 05/19/2023 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/integrated-planning/PDSD/PDSD_Owner_Builder_Affidavit.pdf, is required prior to issuance of permit. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0223-02974
Permit Description: Bedroom Bathroom Addition
Total Completed Inspections - 16
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/22/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Addition footings and footings for family room. Ok to place concrete in progress areas. | |
| 07/11/2023 | COT - RSBU - Preslab | Passed | ||
| 08/03/2023 | RSEL - Electrical Progress | Passed | ||
| 08/08/2023 | BULD - Electrical Clearance | Passed | Approved service upgrade, INCR Clearance to TEP is required for the cutover | |
| 08/25/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Need fire foam all openings, photo of completion by today, ok to continue once photos have been submitted. | |
| 08/25/2023 | RSME - Mechanical Progress | Passed | ok to insulate after fire foaming openings | |
| 08/25/2023 | RSPL - Plumbing Progress | Passed | under pressure all good to continue. | |
| 08/31/2023 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 03/26/2024 | RSBU - Building Final | Passed | ||
| 03/26/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 03/26/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 03/26/2024 | COT - RSEL - Electrical Final | Passed | ||
| 03/26/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 03/26/2024 | COT - RSME - Mechanical Final | Passed | ||
| 03/26/2024 | COT - RSPL - Rough Soil | Passed | ||
| 03/26/2024 | COT - RSPL - Plumbing Final | Passed |