Permit: TC-RES-0126-00062
Permit Details
Status:
Inspections
Type:
Residential Building - One or Two Family
Address:
2046 E 4TH ST
Address NEW:
2046 E 4TH ST
Apply Date:
01/06/2026
Applicant:
TFS Solar
Description:
New Ground Mounted Structure for 8.60 kW DC photovoltaic solar system; 20 modules; 27 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings. 1 battery expansion pack, (no inverter). Trench from array to (E) Garage. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
Permit Reviews
Permit Number - TC-RES-0126-00062
Permit Status: Inspections
Permit Description: New Ground Mounted Structure for 8.60 kW DC photovoltaic solar system; 20 modules; 27 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings. 1 battery expansion pack, (no inverter). Trench from array to (E) Garage. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/06/2026 | RESIDENTIAL SOLAR v.1 | 01/13/2026 | APPROVED |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-RES-0126-00062
Permite Description: New Ground Mounted Structure for 8.60 kW DC photovoltaic solar system; 20 modules; 27 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings. 1 battery expansion pack, (no inverter). Trench from array to (E) Garage. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/15/2026 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Not Ready | Footers were poured prior to rebar inspection. 6/15/2026 |
| 06/15/2026 | COT - RSOL - Electrical Underground Solar Project | N/A | Partial Pass | Partial pass. X2 1" schedule 40 conduit at an 18" depth from new structure to a box (pull point) behind inverter. Okay to backfill progress areas. Ensure caution tape is in place after 1st lift of compaction. 6/15/2026 |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-RES-0126-00062
Permit Description: New Ground Mounted Structure for 8.60 kW DC photovoltaic solar system; 20 modules; 27 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings. 1 battery expansion pack, (no inverter). Trench from array to (E) Garage. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/16/2026 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Approved per third party report. 6/16/2026 | |
| 06/16/2026 | COT - RSOL - Electrical Underground Solar Project | Passed | ||
| 06/16/2026 | BULD - Electrical Clearance | Passed | Clearance for TEP DGC/BAT. 6/16/2026 | |
| 06/16/2026 | RSBU - Building Final | Passed | ||
| 06/16/2026 | COT - RSOL - Electrical Final Solar Project | Passed |