Permit: TC-RES-0125-00249
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
1421 W BRONTE PL
Address NEW:
1421 W BRONTE PL
Apply Date:
01/15/2025
Applicant:
Tim Willsey
Description:
Maintenance of existing PV system. Like for like replacement of L2 wire between main service panel and inverter and DG meter guts. New DG clearance will be required by TEP.
Permit Reviews
Permit Number - TC-RES-0125-00249
Permit Status: Complete
Permit Description: Maintenance of existing PV system.
Like for like replacement of L2 wire between main service panel and inverter and DG meter guts.
New DG clearance will be required by TEP.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/04/2025 | RESIDENTIAL SOLAR v.2 | 03/10/2025 | APPROVED |
| 01/16/2025 | RESIDENTIAL SOLAR v.1 | 01/31/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-RES-0125-00249
Permit Status: Complete
Permit Description: Maintenance of existing PV system.
Like for like replacement of L2 wire between main service panel and inverter and DG meter guts.
New DG clearance will be required by TEP.
| Date | Description | Comments |
|---|---|---|
| 01/30/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-RES-0125-00249
Permite Description: Maintenance of existing PV system.
Like for like replacement of L2 wire between main service panel and inverter and DG meter guts.
New DG clearance will be required by TEP.
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/14/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0125-00249
Permit Description: Maintenance of existing PV system.
Like for like replacement of L2 wire between main service panel and inverter and DG meter guts.
New DG clearance will be required by TEP.
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/14/2025 | BULD - Electrical Clearance | Passed | Approved solar maintenance - DGC Clearance is required for the solar meter | |
| 03/14/2025 | COT - RSOL - Electrical Final Solar Project | Passed |