Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Address:
4418 E 14TH ST
Address NEW:
4418 E 14TH ST
Apply Date:
01/15/2025
Applicant:
Liam Atchley
Description:
Install 22kw Generator, sub panel, transfer switch, and dedicated gas line

Permit Reviews

Permit Number - TC-RES-0125-00246
Permit Status: Complete
Permit Description: Install 22kw Generator, sub panel, transfer switch, and dedicated gas line
Start Date Submittal Complete Date Status  
01/16/2025 RESIDENTIAL SIMPLE REVIEW v.1 01/16/2025 APPROVED Review Details

Conditions

Permit Number - TC-RES-0125-00246
Permit Status: Complete
Permit Description: Install 22kw Generator, sub panel, transfer switch, and dedicated gas line
Date Description Comments
01/16/2025 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.

Completed Inspections

Permit Status: Complete
Permit Number: TC-RES-0125-00246
Permit Description: Install 22kw Generator, sub panel, transfer switch, and dedicated gas line
Total Completed Inspections - 5
Date Description Inspector Results Comments
03/26/2025 BULD - Electrical Clearance Passed Approved electric generator installation - AG Clearance to TEP is required
03/26/2025 COT - RSEL - Electrical Final Passed Approved electric generator installation - AG Clearance to TEP is required
Pending gas and mechanical finals
04/02/2025 COT - RSPL - Plumbing Final Passed Approved generator installation
04/02/2025 COT - RSME - Mechanical Final Passed
04/02/2025 COT - BULD - SWG Clearance Passed Approved generator installation - SWG Clearance is required

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW