Permit: TC-RES-0123-01946
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
6251 E SUNNY DR
Address NEW:
6251 E SUNNY DR
Apply Date:
01/08/2023
Applicant:
Franco Chimienti
Description:
New garage.
Permit Reviews
Permit Number - TC-RES-0123-01946
Permit Status: Complete
Permit Description: New garage.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/20/2023 | RESTAMP - RESIDENTIAL v.1 | 04/28/2023 | APPROVED |
| 03/23/2023 | RESIDENTIAL NEW DWELLING v.2 | 04/20/2023 | APPROVED |
| 01/12/2023 | RESIDENTIAL NEW DWELLING v.1 | 03/22/2023 | REQUIRES RESUBMIT |
| 07/18/2023 | RESIDENTIAL NEW DWELLING v.1 | 07/24/2023 | APPROVED |
Conditions
Permit Number - TC-RES-0123-01946
Permit Status: Complete
Permit Description: New garage.
| Date | Description | Comments |
|---|---|---|
| 04/28/2023 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/integrated-planning/PDSD/PDSD_Owner_Builder_Affidavit.pdf, is required prior to issuance of permit. | |
| 01/20/2023 | A final elevation certificate is required before the final inspection | |
| 01/20/2023 | An intermediate elevation certificate is required before the Pre-Slab inspection |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-RES-0123-01946
Permite Description: New garage.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/18/2023 | COT - RSBU - Interior Shear Bracing | N/A | Not Applicable | |
| 11/27/2023 | COT - RSME - Mechanical Final | N/A | Not Applicable | No mechanical equipment in garage. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0123-01946
Permit Description: New garage.
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/01/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 09/01/2023 | COT - RSBU - Preslab | Passed | ||
| 10/18/2023 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 10/18/2023 | COT - RSBU - Roof Nailing | Passed | ||
| 10/23/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Rough framing is complete, roof trusses and decking are installed, rough-in of electrical panel and boxes is complete. Okay to proceed with roofing and interior trim out. | |
| 11/27/2023 | COT - RSBU - Stem Wall/Retaining Wall | Passed | No stem wall, garage is slab on grade with exterior walls attached to slab. | |
| 11/27/2023 | BULD - Electrical Clearance | Passed | ||
| 11/27/2023 | COT - RSEL - Electrical Final | Passed | All garage outlets are on a GFCI Receptacle. | |
| 11/27/2023 | RSEL - Electrical Progress | Passed | ||
| 11/27/2023 | COT - RSEL - Outdoor Lighting | Passed | Exterior lights are properly installed and per plans. |